Recital 3, Decision_act (EU) 2017/178

In forcesince 31 Jan 2017

The letter of intent dated 27 April 2014 stated that the extension from Katowice to Medyka could only be operational in 2020. However, Implementing Decision (EU) 2015/1111 also covers this extension and in accordance with Article 5(7) of Regulation (EU) No 913/2010, the Member States concerned should build the freight corridor at the latest two years after the Commission's Decision is published. Based on this, the extension to Medyka would have to be operational by 7 July 2017 at the latest; this does not correspond to the intention specified in the Member States' letter. Implementing Decision (EU) 2015/1111 should therefore be amended by removing the reference to extending the North Sea-Baltic rail freight corridor to Medyka.