ANNEX 2, Decision_act (EU) 2015/1478

In forcesince 19 Aug 2015

The purpose of this document, Annex 2 to the Statutes, is to describe the overall cost estimates, the budget and the planned schedule for the ESS project. It is a high-level summary of the performance baseline established in spring 2014, based on the TDR and associated documents presented to the ESS Steering Committee in 2012 and in line with the technical and scientific scope summarised in Annex 1. All cost figures in this document are on the price basis of January 2013.

The costing and planning for ESS has been made with a life cycle approach, and as such includes all the different phases of the facility's lifetime. The phases included in the costing and planning are the pre-construction, construction, operations (comprising the initial operations and the steady-state operations) and decommissioning phases. The total life cycle cost is shown in Figure 1 below.

The cost for pre-construction includes the design update phase of the facility. The pre-construction costs are summed up to 80 M EUR and include both cash and in-kind contributions.

The construction budget is 1843 M EUR, and it includes capital costs from the construction phase start 1 January 2013, to the start of the steady-state operations in 2026. The construction budget includes the capital investment for 16 instruments.

During the period 2019-2025 there will be an initial operations phase in parallel to the construction phase. Initial operations amounts to 810 M EUR and includes the budgets to operate the entire facility and to meet the TDR goal of a 22-instrument suite. The breakdown of the budget on construction project level is shown in Figure 2. It includes both cash and in-kind contributions.

The initial operations phase begins with the production, delivery and detection of the first neutrons. The budget includes costs for start-up of machine operations, ramping up of beam power, the start of the user programme, the first spares and the main contribution to the construction of the six remaining instruments to complete the baseline suite of 22 instruments. The initial operations budget is planned to end in 2025, providing a smooth transition to the budget for the steady-state operations.

The budget for steady-state operations will start in 2026 and continue until 2065 and includes all foreseen costs for sustainable operations in accordance with Annex 1. It includes a small contribution for completing the instrument suite in the first years and for keeping it competitive during steady-state operations. The steady-state operations budget in steady state is 140 M EUR/year.

According to the life cycle approach, it is planned for that after the operations phase, ESS will be decommissioned and the site restored for other use. The associated costs are included in the decommissioning budget, summing up to 177 M EUR.

The high-level schedule for pre-construction, construction, initial operations and steady-state operations is shown in Figure 4 below. The schedule is technically constrained in the sense that resources (manpower and funding) are assumed not to be delayed.

The budget profile for the construction phase (2013-2025), the initial operations (2019-2025) together with the first year of steady-state operations (2026- ) is shown in Figure 5 below. It includes both cash and in-kind contributions. The planned spending profile is based on best estimates assuming a technically constrained schedule.

The total number of staff during steady-state operations is 494. The planned staffing profile for the steady-state operations, stated in full-time equivalents (FTEs), is shown in Figure 6 below.

Figure 6 above includes the staff for DMSC with a planned staff level in steady-state operations of 60-65 FTE. The staffing of the ESS DMSC will be gradually ramped up.