Art. 48 Commission Implementing Regulation (EU) No 809/2014 of 17 July 2014 laying down rules fo…

Administrative checks

In forcesince 10 Jun 2019cited 11×
1.

Administrative checks shall be carried out on all applications for support, payment claims or other declarations required to be submitted by a beneficiary or a third party, and shall cover all elements that can be checked and are appropriate to be checked by means of administrative checks. The procedures shall require recording of the control work undertaken, the results of the verification and the measures taken in the event of discrepancies.

2.

Administrative checks on applications for support shall ensure the compliance of the operation with applicable obligations established by Union or national law or by the rural development programme, including those of public procurement, State aid and other obligatory standards and requirements. The checks shall in particular include verification of:

(a)

the eligibility of the beneficiary;

(b)

the eligibility criteria, commitments and other obligations of the operation for which support is requested;

(c)

compliance with the selection criteria, where those criteria apply;

(d)

the eligibility of the costs of the operation, including compliance with the category of costs or calculation method to be used when the operation or part of it falls under Article 67(1)(b), (c) and (d) of Regulation (EU) No 1303/2013;

(e)

for costs referred to in Article 67(1)(a) of Regulation (EU) No 1303/2013, excluding contributions in kind and depreciation, a verification of the reasonableness of the costs submitted. The costs shall be evaluated using a suitable evaluation system, such as reference costs, a comparison of different offers or an evaluation committee. For operations with a support rate up to 30 % or for operations supported under Article 35 of Regulation (EU) No 1305/2013, the verification of the reasonableness of the costs may be carried out at the stage of the administrative checks on payment claims. For operations with eligible costs up to EUR 5000, the reasonableness of the costs may be established by a draft budget agreed ex ante by the managing authority.

3.

Administrative checks on payment claims shall include in particular, and where appropriate for the claim in question, verification of:

(a)

the completed operation compared with the operation for which the application for support was granted;

(b)

the costs incurred and the payments made, except where a form or method as referred to in Article 67(1)(b), (c) or (d) of Regulation (EU) No 1303/2013 is applied.

4.

Administrative checks shall include procedures to avoid irregular double financing with other Union or national schemes and with the previous programming period. Where financing from other sources exists, those checks shall ensure that the total support received does not breach the maximum permissible amounts or support rates.

5.

Administrative checks on investment operations shall include at least one visit to the operation supported or the investment site to verify the realisation of the investment.

However, the competent authority may decide not to carry out such visits for duly justified reasons, such as the following:

(a)

the operation is included in the sample for an on-the-spot check to be carried out in accordance with Article 49;

(b)

the competent authority considers that the operation in question is a small investment;

(c)

the competent authority considers that the risk that the conditions for receiving support are not met is low, or that the risk that the investment has not been realised is low.

The decision referred to in the second subparagraph and its justification shall be recorded.

6.

As regards the financial instruments referred to in Article 38(1)(b) and (c) of Regulation (EU) No 1303/2013, paragraphs 1 to 5 of this Article shall neither apply to the contribution to the financial instrument nor to the support to the final recipient. However, Articles 58 and 59 of Regulation (EU) No 1306/2013 and Article 9 of Commission Delegated Regulation (EU) No 480/2014 [Commission Delegated Regulation (EU) No 480/2014 of 3 March 2014 supplementing Regulation (EU) No 1303/2013 of the European Parliament and of the Council laying down common provisions on the European Regional Development Fund, the European Social Fund, the Cohesion Fund, the European Agricultural Fund for Rural Development and the European Maritime and Fisheries Fund and laying down general provisions on the European Regional Development Fund, the European Social Fund, the Cohesion Fund and the European Maritime and Fisheries Fund (OJ L 138, 13.5.2014, p. 5).] shall apply.

The 10 that are cited most themselves, of 11.

  • Regulation (EU) 2020/5326Lawamends

    Чрез дерогация от член 48, параграф 5 от Регламент за изпълнение (ЕС) № 809/2014, когато поради мерките, предприети във връзка с …

  • Regulation (EU) 2021/7251Lawamends

    Чрез дерогация от член 24, параграф 4, член 48, параграф 5, член 49, параграф 1, член 52, параграф 1, член 60, параграф 2, трета алинея и член 71, …

  • Arrêt du Tribunal (troisième chambre) du 30 juin 2021. République italienne contre Commission européenne.Decision

    Ce faisant, l’ARCEA a commis un manquement manifeste à l’obligation qui lui incombait, conformément à l’article 74, paragraphe 1, du règlement n o 1306/2013, de vérifier si les conditions d’éligibilité des dépenses étaient …

    30 Jun 2021 · 62019TJ0265

  • Judgment of the Court (Seventh Chamber) of 1 December 2022. DELID v Izpalnitelen direktor na Darzhaven fond „Zemedelie“.Decision

    In this instance, it must be held that the requirement, laid down by the national legislation, according to which the grant of the support referred to in that provision is conditional upon the person applying for support submitting a …

    1 Dec 2022 · 62021CJ0409

  • Decision_act (EU) 2020/859Law

    … | Мярка 125 и мярка 04.3: несъответстващи разходи във връзка с член 48, параграф 3 от Регламент 809/2014 – финансови години 2015 и 2016 | …

  • Arrêt du Tribunal (quatrième chambre) du 9 mars 2022. République italienne contre Commission européenne.Decision

    … publics – Article 24, paragraphe 2, sous c), et article 26, paragraphe 1, sous d), du règlement (UE) no 65/2011 – Article 48, paragraphe 2, et article 51, paragraphe 1, du règlement d’exécution (UE) no 809/2014 – Risque de …

    9 Mar 2022 · 62020TJ0010

  • Regulation (EU) 2019/936Lawamends

  • Decision_act (EU) 2024/1690Law

    … проверка — Подходяща оценка на основателността на разходите (член 48, параграф 2, буква д) от Регламент (ЕС) № 809/2014 и член 67 от …

  • Regulation (EU) 2022/12161Lawamends

    Чрез дерогация от член 24, параграф 4, член 48, параграф 5, член 49, параграф 1, член 52, параграф 1, член 60, параграф 2, трета алинея и член 71, …

  • Commission Implementing Regulation (EU) 2020/532 of 16 April 2020 derogating in respect…6Law

    By way of derogation from Article 48(5) of Implementing Regulation (EU) No 809/2014, where due to the measures put in place to address the pandemic of COVID-19 Member States are not in a position to carry out any visit to the operation …