The first three-year work programme period referred to in Article 29(1) of Regulation (EU) No 1308/2013 shall start on 1 April 2015. The following periods shall start every three years on 1 April.
Each recipient organisation recognised under Regulation (EU) No 1308/2013 may submit an approval application for one single work programme by a date to be laid down by the Member State but no later than 15 February of each year.
The approval application shall contain the following information:
details of the recipient organisation concerned;
information relating to the selection criteria laid down in Article 6(1);
a description of and the justification and implementation timetable for each proposed measure;
the expenditure plan, broken down by measure and area as referred to in Article 3(1), with details for each 12-month period from the date of approval of the work programme, distinguishing between the overheads, which must not exceed 5 % of the total, and the other main types of costs;
the funding plan for each area referred to in Article 3(1), with details for each 12-month period at most from the date of approval of the work programme, indicating in particular the Union funding applied for and, where applicable, the financial contributions from recipient organisations and the contribution from the Member State;
a description of the quantitative and qualitative efficiency indicators enabling evaluation during implementation and ex-post evaluation of the programme on the basis of the general principles laid down by the Member State;
proof that a security has been provided in accordance with Commission Implementing Regulation (EU) No 282/2012 [Commission Implementing Regulation (EU) No 282/2012 of 28 March 2012 laying down common detailed rules for the application of the system of securities for agricultural products (OJ L 92, 30.3.2012, p. 4).];
an application for an advance;
the declaration stipulated in Article 4(2);
for recipient organisations, details of the recipient organisations responsible for actually carrying out the subcontracted activities contained in their programmes;
a declaration that the measures provided for in the recipient organisations' programmes do not form the subject of another application for Union funding under this Regulation.
For the purposes of point (d) of the first subparagraph, Member States may decide whether overheads are eligible on the basis of a flat rate or of actual costs established on the basis of supporting documents to be submitted by the beneficiaries.
Final approval of a work programme may be subject to the incorporation of amendments deemed necessary by the Member State. In that case, the recipient organisation concerned shall communicate its agreement within 15 days of the amendments being notified.
Member States shall ensure that the Union funding is allocated within each category of recipients, taking into account the value of the olive oil produced or marketed by the members of the recipient organisations.
No later than 15 March each year, each Member State shall inform the recipient organisations of the work programmes which have been approved and, where applicable, of the work programmes to which it is granting the corresponding national funding.
If a proposed work programme is not selected, the Member State shall immediately release the security referred to in paragraph 3 point (g).