Experts involved in the preparation of environmental impact assessment reports should be qualified and competent. Sufficient expertise, in the relevant field of the project concerned, is required for the purpose of its examination by the competent authorities in order to ensure that the information provided by the developer is complete and of a high level of quality.
Recital 33, Directive (EU) 2014/52
In forcesince 16 Apr 2014cited 1×
Judgment of the Court (Tenth Chamber) of 1 August 2025. Asociación Petón do Lobo v Dirección Xeral de Planificación Enerxética Recursos NatuDecision
Recitals 31 to 33 and 36 of Directive 2014/52 are worded as follows: ‘(31) The environmental impact assessment report to be provided by the developer for a project should include a description of reasonable alternatives studied by the …
1 Aug 2025 · 62024CJ0461