The risk rating system shall provide the basis for a targeted selection of vehicles operated by undertakings with a poor record concerning compliance with vehicle maintenance and roadworthiness requirements. It shall take into account results from both periodic roadworthiness tests and technical roadside inspections.
The risk rating System shall consider the following parameters for determining a risk rating for the undertaking concerned:
number of deficiencies
severity of deficiencies
number of technical roadside inspections or periodic and voluntary roadworthiness tests
time factor
The deficiencies shall be weighted according to their severity, using the following severity factors:
—Dangerous deficiency40
—Major deficiency10
—Minor deficiency1
The evolution of an undertaking’s (vehicle’s) situation shall be reflected by applying a lower weighting to ‘older’ inspection results (deficiencies) than to more ‘recent’ ones, using the following factors:
Year 1 = last 12 months = factor 3
Year 2 = months 13-24 = factor 2
Year 3 = months 25-36 = factor 1
This shall only apply for the calculation of the overall risk rating.
The risk rating shall be calculated using the following formulas:
The formula for the overall risk rating:
RR
DY13DY22DY31
#CY1#CY2#CY3
Where
RRoverall risk rating score
DYitotal for the defects in year 1, 2, 3
DY1#DD40#MaD10#MiD1 in year 1
#…number of…
DDdangerous deficiencies
MaDmajor deficiencies
MiDminor deficiencies
Cchecks (technical roadside inspections or periodic and voluntary roadworthiness tests) in year 1, 2, 3
The formula for the annual risk rating:
AR
#DD40#MaD10#MiD1
#C
Where
ARannual risk score
#…number of…
DDdangerous deficiencies
MaDmajor deficiencies
MiDminor deficiencies
Cchecks (technical roadside inspections or periodic and voluntary roadworthiness tests)
The annual risk shall be used to assess the evolution of an undertaking over the years.
The classification of undertakings (vehicles) based on the overall risk rating shall be performed in such a way that the following distribution within the listed undertakings (vehicles) is reached:
< 30 % low risk
30-80 % medium risk
> 80 % high risk.