Art. 89 Directive (EU) 2014/25

Modification of contracts during their term

In forcesince 26 Feb 2014cited 8×
1.

Contracts and framework agreements may be modified without a new procurement procedure in accordance with this Directive in any of the following cases:

(a)

where the modifications, irrespective of their monetary value, have been provided for in the initial procurement documents in clear, precise and unequivocal review clauses, which may include price revision clauses, or options. Such clauses shall state the scope and nature of possible modifications or options as well as the conditions under which they may be used. They shall not provide for modifications or options that would alter the overall nature of the contract or framework agreement;

(b)

for additional works, services or supplies by the original contractor, irrespective of their value, that have become necessary and were not included in the initial procurement where a change of contractor:

(i)

cannot be made for economic or technical reasons such as requirements of interchangeability or interoperability with existing equipment, software, services or installations procured under the initial procurement; and

(ii)

would cause significant inconvenience or substantial duplication of costs for the contracting entity;

(c)

where all of the following conditions are fulfilled:

(i)

the need for modification has been brought about by circumstances which a diligent contracting entity could not foresee;

(ii)

the modification does not alter the overall nature of the contract;

(d)

Where a new contractor replaces the one to which the contracting entity had initially awarded the contract as a consequence of either:

(i)

an unequivocal review clause or option in conformity with point (a),

(ii)

universal or partial succession into the position of the initial contractor, following corporate restructuring, including takeover, merger, acquisition or insolvency, of another economic operator that fulfils the criteria for qualitative selection initially established provided that this does not entail other substantial modifications to the contract and is not aimed at circumventing the application of this Directive; or

(iii)

in the event that the contracting entity itself assumes the main contractor’s obligations towards its subcontractors where this possibility is provided for under national legislation pursuant to Article 88;

(e)

where the modifications, irrespective of their value, are not substantial within the meaning of paragraph 4.

Contracting entities having modified a contract in the cases set out under points (b) and (c) of this paragraph shall publish a notice to that effect in the Official Journal of the European Union. Such notice shall contain the information set out in Annex XVI and shall be published in accordance with Article 71.

2.

Furthermore, and without any need to verify whether the conditions set out under points (a) to (d) of paragraph 4 are met, contracts may equally be modified without a new procurement procedure in accordance with this Directive being necessary where the value of the modification is below both of the following values:

(i)

the thresholds set out in Article 15; and

(ii)

10 % of the initial contract value for service and supply contracts and below 15 % of the initial contract value for works contracts.

However, the modification may not alter the overall nature of the contract or framework agreement. Where several successive modifications are made, the value shall be assessed on the basis of the net cumulative value of the successive modifications.

3.

For the purpose of the calculation of the price referred to in paragraph 2, the updated price shall be the reference value when the contract includes an indexation clause.

4.

A modification of a contract or a framework agreement during its term shall be considered to be substantial within the meaning of point (e) of paragraph 1, where it renders the contract or the framework agreement materially different in character from the one initially concluded. In any event, without prejudice to paragraphs 1 and 2, a modification shall be considered to be substantial where one or more of the following conditions is met:

(a)

the modification introduces conditions which, had they been part of the initial procurement procedure, would have allowed for the admission of other candidates than those initially selected or for the acceptance of a tender other than that originally accepted or would have attracted additional participants in the procurement procedure;

(b)

the modification changes the economic balance of the contract or the framework agreement in favour of the contractor in a manner which was not provided for in the initial contract or framework agreement;

(c)

the modification extends the scope of the contract or framework agreement considerably;

(d)

where a new contractor replaces the one to which the contracting entity had initially awarded the contract in other cases than those provided for under point (d) of paragraph 1.

5.

A new procurement procedure in accordance with this Directive shall be required for other modifications of the provisions of a works, supply or service contract or a framework agreement during its term than those provided for under paragraphs 1 and 2.

  • Regulation (EU) 2019/17802Law

    … за изменение на договор — Общата директива таблица 2, колона 39 | член 89, параграф 1 от Директива 2014/25/ЕС | Обявление за изменение на …

  • Regulation (EU) 2023/2884Law

    … за изменение на договор — Общата директива таблица 2, колона 39 | член 89, параграф 1 от Директива 2014/25/ЕС | Обявление за изменение на …

  • Judgment of the Court (Fourth Chamber) of 14 May 2020. T-Systems Magyarország Zrt. and BKK Budapesti Közlekedési Központ v Közbeszerzési HatDecisioninterprets

    Title II of Directive 2014/25, which is entitled ‘Rules applicable to contracts’, includes, inter alia, Chapter IV on ‘contract enforcement’, which contains Articles 87 to 90 of that directive. Article 89, which is itself entitled …

    14 May 2020 · 62019CJ0263

  • Opinion of Advocate General Mengozzi delivered on 25 November 2015. MT Højgaard A/S and Züblin A/S v Banedanmark.Decision

    In that regard, it should also be noted that, as some of the interveners have pointed out, the principle of equal treatment for tenderers is likely to play a fundamental role before the contract is awarded, when the various tenderers are …

    25 Nov 2015 · 62014CC0396

  • Opinion of Advocate General Campos Sánchez-Bordona delivered on 17 October 2024. Fastned Deutschland GmbH & Co. KG v Die Autobahn GmbH des BDecision

    From a contextual point of view, the requirement that the original award must have been lawful, as an essential condition for subsequent modification without a call for tenders, does not feature in any of the cases provided for in Article …

    17 Oct 2024 · 62023CC0452

  • Opinion of Advocate General Rantos delivered on 30 April 2025. Polismyndigheten v Konkurrensverket.Decision

    Of those six situations, the last two referred to appear relevant to the present case. Indeed, given that the value of the contested modifications, in the case of one of the two contested framework agreements, is below the de minimis …

    30 Apr 2025 · 62024CC0282

  • Opinion of Advocate General Bobek delivered on 21 November 2019. HUNGEOD Közlekedésfejlesztési, Földmérési, Út- és Vasúttervezési Kft. and ODecision

    First, in so far as public contracts fall within the scope ratione materiae of the public procurement directives, modifications of them are also governed by EU law. [See, to that effect, judgments of 19 June 2008, pressetext …

    21 Nov 2019 · 62018CC0496

  • Arrêt du Tribunal (quatrième chambre) du 23 juillet 2025 (Extraits). BT Global Services Belgium contre Commission européenne.Decision

    … paragraphe 1, point c), de la directive 2014/23/UE ; article 72, paragraphe 1, point c), de la directive 2014/24/UE ; article 89, paragraphe 1, point c), de la directive 2014/25/UE] […] La nécessité de continuer à fonctionner sur …

    23 Jul 2025 · 62023TJ1081