Art. 90 Directive (EU) 2014/24

Transposition and transitional provisions

In forcesince 26 Feb 2014cited 29×
1.

Member States shall bring into force the laws, regulations and administrative provisions necessary to comply with this Directive by 18 April 2016. They shall forthwith communicate to the Commission the text of those measures.

2.

Notwithstanding paragraph 1 of this Article, Member States may postpone the application of Article 22(1) until 18 October 2018, except where use of electronic means is mandatory pursuant to Articles 34, 35 or 36, Article 37(3), Article 51(2) or Article 53.

Notwithstanding paragraph 1 of this Article, Member States may postpone the application of Article 22(1) for central purchasing bodies until 18 April 2017.

Where a Member State chooses to postpone the application of Article 22(1), that Member State shall provide that contracting authorities may choose between the following means of communication for all communication and information exchange:

(a)

electronic means in accordance with Article 22;

(b)

post or other suitable carrier;

(c)

fax;

(d)

a combination of those means.

3.

Notwithstanding paragraph 1 of this Article, Member States may postpone the application of the second subparagraph of Article 59(2) until 18 April 2018.

4.

Notwithstanding paragraph 1 of this Article, Member States may postpone the application of the second subparagraph of Article 59(5) until 18 October 2018.

5.

Notwithstanding paragraph 1 of this Article, Member States may postpone the application of Article 61(2) until 18 October 2018.

6.

When Member States adopt the measures referred to in paragraphs 1 to 5, they shall contain a reference to this Directive or be accompanied by such a reference on the occasion of their official publication. Member States shall determine how such reference is to be made.

7.

Member States shall communicate to the Commission the text of the main provisions of national law which they adopt in the field covered by this Directive.

The 10 that are cited most themselves, of 29.

  • Judgment of the Court (Fourth Chamber) of 14 January 2021. RTS infra BVBA and Aannemingsbedrijf Norré-Behaegel v Vlaams Gewest.Decision

    As a preliminary point, it should be noted that, given that the provisions of Article 57(6) of Directive 2014/24, the interpretation of which is sought, do not correspond to any provision in the EU legislation applicable to public …

    14 Jan 2021 · 62019CJ0387

  • Judgment of the Court (First Chamber) of 7 April 2016. Partner Apelski Dariusz v Zarząd Oczyszczania Miasta.Decision

    Under Article 90(1) of that directive: ‘Member States shall bring into force the laws, regulations and administrative provisions necessary to comply with this Directive by 18 April 2016. …’

    7 Apr 2016 · 62014CJ0324

  • Judgment of the Court (Fourth Chamber) of 27 October 2016. Hörmann Reisen GmbH v Stadt Augsburg and Landkreis Augsburg.Decision

    Under the first sentence of Article 90(1) of Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing Directive 2004/18 (OJ 2014 L 94, p. 65): ‘Member States shall bring …

    27 Oct 2016 · 62015CJ0292

  • Judgment of the Court (Fifth Chamber) of 27 November 2019. Tedeschi Srl and Consorzio Stabile Istant Service v C.M. Service Srl and UniversiDecision

    Article 90(1) of Directive 2014/24 provides: ‘Member States shall bring into force the laws, regulations and administrative provisions necessary to comply with this Directive by 18 April 2016. …’

    27 Nov 2019 · 62018CJ0402

  • Regulation (EU) 2016/7Law

    … [Вж.: член 90, параграф 3 от Директива 2014/24/ЕС.]. Това означава, че както изцяло електронната версия на ЕЕДОП, така и версията на хартиен …

  • Judgment of the Court (Ninth Chamber) of 20 September 2018. Stefan Rudigier.Decision

    In accordance with Article 90(1) and Article 91 of the directive, entitled respectively ‘Transposition and transitional provisions’ and ‘Repeals’, the Member States were to comply with the directive at the latest by 18 April 2016, …

    20 Sep 2018 · 62017CJ0518

  • Ordonnance de la Cour (sixième chambre) du 10 novembre 2016. Spinosa Costruzioni Generali SpA et Melfi Srl contre Comune di Monteroduni.Decision

    L’article 90 de la directive 2014/24 dispose que les États membres doivent mettre en vigueur les dispositions législatives, réglementaires et administratives nécessaires pour se conformer à cette directive au plus tard le 18 avril …

    10 Nov 2016 · 62016CO0162

  • Ordonnance de la Cour (sixième chambre) du 10 novembre 2016. Edra Costruzioni Soc. coop. et Edilfac Srl contre Comune di Maiolati Spontini.Decision

    L’article 90 de la directive 2014/24 dispose que les États membres doivent mettre en vigueur les dispositions législatives, réglementaires et administratives nécessaires pour se conformer à cette directive au plus tard le 18 avril …

    10 Nov 2016 · 62016CO0140

  • Opinion of Advocate General Jääskinen delivered on 8 September 2015. Partner Apelski Dariusz v Zarząd Oczyszczania Miasta.Decision

    Article 90(1) of Directive 2014/24 entitled ‘[t]ransposition and transitional provisions’ states that ‘Member States shall bring into force the laws, regulations and administrative provisions necessary to comply with this Directive …

    8 Sep 2015 · 62014CC0324

  • Opinion of Advocate General Campos Sánchez-Bordona delivered on 17 September 2020. RTS infra BVBA and Aannemingsbedrijf Norré-Behaegel v VlaDecision

    The time limit for transposing Directive 2014/24 expired, in accordance with Article 90 thereof, on 18 April 2016, on which date Directive 2004/18 was repealed.

    17 Sep 2020 · 62019CC0387