Art. 72 Directive (EU) 2014/24

Modification of contracts during their term

In forcesince 26 Feb 2014cited 28×
1.

Contracts and framework agreements may be modified without a new procurement procedure in accordance with this Directive in any of the following cases:

(a)

where the modifications, irrespective of their monetary value, have been provided for in the initial procurement documents in clear, precise and unequivocal review clauses, which may include price revision clauses, or options. Such clauses shall state the scope and nature of possible modifications or options as well as the conditions under which they may be used. They shall not provide for modifications or options that would alter the overall nature of the contract or the framework agreement;

(b)

for additional works, services or supplies by the original contractor that have become necessary and that were not included in the initial procurement where a change of contractor:

(i)

cannot be made for economic or technical reasons such as requirements of interchangeability or interoperability with existing equipment, services or installations procured under the initial procurement; and

(ii)

would cause significant inconvenience or substantial duplication of costs for the contracting authority.

However, any increase in price shall not exceed 50 % of the value of the original contract. Where several successive modifications are made, that limitation shall apply to the value of each modification. Such consecutive modifications shall not be aimed at circumventing this Directive;

(c)

where all of the following conditions are fulfilled:

(i)

the need for modification has been brought about by circumstances which a diligent contracting authority could not foresee;

(ii)

the modification does not alter the overall nature of the contract;

(iii)

any increase in price is not higher than 50 % of the value of the original contract or framework agreement. Where several successive modifications are made, that limitation shall apply to the value of each modification. Such consecutive modifications shall not be aimed at circumventing this Directive;

(d)

where a new contractor replaces the one to which the contracting authority had initially awarded the contract as a consequence of either:

(i)

an unequivocal review clause or option in conformity with point (a);

(ii)

universal or partial succession into the position of the initial contractor, following corporate restructuring, including takeover, merger, acquisition or insolvency, of another economic operator that fulfils the criteria for qualitative selection initially established provided that this does not entail other substantial modifications to the contract and is not aimed at circumventing the application of this Directive; or

(iii)

in the event that the contracting authority itself assumes the main contractor’s obligations towards its subcontractors where this possibility is provided for under national legislation pursuant to Article 71;

(e)

where the modifications, irrespective of their value, are not substantial within the meaning of paragraph 4.

Contracting authorities having modified a contract in the cases set out under points (b) and (c) of this paragraph shall publish a notice to that effect in the Official Journal of the European Union. Such notice shall contain the information set out in Annex V part G and shall be published in accordance with Article 51.

2.

Furthermore, and without any need to verify whether the conditions set out under points (a) to (d) of paragraph 4 are met, contracts may equally be modified without a new procurement procedure in accordance with this Directive being necessary where the value of the modification is below both of the following values:

(i)

the thresholds set out in Article 4; and

(ii)

10 % of the initial contract value for service and supply contracts and below 15 % of the initial contract value for works contracts.

However, the modification may not alter the overall nature of the contract or framework agreement. Where several successive modifications are made, the value shall be assessed on the basis of the net cumulative value of the successive modifications.

3.

For the purpose of the calculation of the price mentioned in paragraph 2 and points (b) and (c) of paragraph 1, the updated price shall be the reference value when the contract includes an indexation clause.

4.

A modification of a contract or a framework agreement during its term shall be considered to be substantial within the meaning of point (e) of paragraph 1, where it renders the contract or the framework agreement materially different in character from the one initially concluded. In any event, without prejudice to paragraphs 1 and 2, a modification shall be considered to be substantial where one or more of the following conditions is met:

(a)

the modification introduces conditions which, had they been part of the initial procurement procedure, would have allowed for the admission of other candidates than those initially selected or for the acceptance of a tender other than that originally accepted or would have attracted additional participants in the procurement procedure;

(b)

the modification changes the economic balance of the contract or the framework agreement in favour of the contractor in a manner which was not provided for in the initial contract or framework agreement;

(c)

the modification extends the scope of the contract or framework agreement considerably;

(d)

where a new contractor replaces the one to which the contracting authority had initially awarded the contract in other cases than those provided for under point (d) of paragraph 1.

5.

A new procurement procedure in accordance with this Directive shall be required for other modifications of the provisions of a public contract or a framework agreement during its term than those provided for under paragraphs 1 and 2.

The 10 that are cited most themselves, of 28.

  • Judgment of the Court (Tenth Chamber) of 7 December 2023. Zamestnik-ministar na regionalnoto razvitie i blagoustroystvoto i rakovoditel na UDecision

    These requests for a preliminary ruling concern the interpretation of Article 72(1)(e) and Article 72(4)(a) and (b) of Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and …

    7 Dec 2023 · 62022CJ0441

  • Judgment of the Court (Fourth Chamber) of 17 June 2021. Simonsen & Weel A/S v Region Nordjylland og Region Syddanmark.Decision

    First, in accordance with the third subparagraph of Article 33(2) and Article 72 of Directive 2014/24, modifications to a framework agreement that are not substantial are allowed, it being understood that, by definition, such a …

    17 Jun 2021 · 62020CJ0023

  • Judgment of the Court (Fourth Chamber) of 12 May 2022. Comune di Lerici v Provincia di La Spezia.Decision

    In that regard, first, Article 72(1)(d)(ii) of Directive 2014/24 provides that a public contract may be modified, without carrying out a new procurement procedure in accordance with the requirements of that directive, where the initial …

    12 May 2022 · 62020CJ0719

  • Judgment of the Court (Fourth Chamber) of 3 February 2022. Advania Sverige AB and Kammarkollegiet v Dustin Sverige AB.Decision

    This request for a preliminary ruling concerns the interpretation of Article 72(1)(d)(ii) of Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing Directive 2004/18/EC …

    3 Feb 2022 · 62020CJ0461

  • Opinion of Advocate General Campos Sánchez-Bordona delivered on 17 October 2024. Fastned Deutschland GmbH & Co. KG v Die Autobahn GmbH des BDecision

    According to the referring court, [Paragraphs 10 and 11 of the order for reference.] the positions adopted before it are set out below. Fastned and Tesla argue that Paragraph 132(1) and (2) of the GWB is not applicable as that provision …

    17 Oct 2024 · 62023CC0452

  • Regulation (EU) 2019/17802Law

    … директива, проекти Изменение на договор | таблица 2, колона 38 | член 72, параграф 1 от Директива 2014/24/ЕС | Обявление за изменение на …

  • Judgment of the Court (Fourth Chamber) of 14 May 2020. T-Systems Magyarország Zrt. and BKK Budapesti Közlekedési Központ v Közbeszerzési HatDecision

    This request for a preliminary ruling concerns, in essence, the interpretation of Article 1(2) and Article 72 of Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing …

    14 May 2020 · 62019CJ0263

  • VwGH 16.06.2020, Ro 2018/04/0015Decision

    … Diese Klauseln dürften aufgrund der gebotenen rechtlichen Beurteilung nicht an den Anforderungen des Art. 72 der Richtlinie 2014/24/EU gemessen werden, weshalb diese die festgestellten Anpassungen in der Vertragsabwicklung jeweils …

    16 Jun 2020 · JWT_2018040015_20200616J00

  • Regulation (EU) 2023/2884Law

    … директива, проекти Изменение на договор | таблица 2, колона 38 | член 72, параграф 1 от Директива 2014/24/ЕС | Обявление за изменение на …

  • Judgment of the Court (Grand Chamber) of 29 April 2025. Fastned Deutschland GmbH & Co. KG v Die Autobahn GmbH des Bundes.Decision

    This request for a preliminary ruling concerns the interpretation of Article 72(1)(c) of Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing Directive 2004/18/EC (OJ …

    29 Apr 2025 · 62023CJ0452