Art. 69 Directive (EU) 2014/24

Abnormally low tenders

In forcesince 26 Feb 2014cited 22×
1.

Contracting authorities shall require economic operators to explain the price or costs proposed in the tender where tenders appear to be abnormally low in relation to the works, supplies or services.

2.

The explanations referred to in paragraph 1 may in particular relate to:

(a)

the economics of the manufacturing process, of the services provided or of the construction method;

(b)

the technical solutions chosen or any exceptionally favourable conditions available to the tenderer for the supply of the products or services or for the execution of the work;

(c)

the originality of the work, supplies or services proposed by the tenderer;

(d)

compliance with obligations referred to in Article 18(2);

(e)

compliance with obligations referred to in Article 71;

(f)

the possibility of the tenderer obtaining State aid.

3.

The contracting authority shall assess the information provided by consulting the tenderer. It may only reject the tender where the evidence supplied does not satisfactorily account for the low level of price or costs proposed, taking into account the elements referred to in paragraph 2.

Contracting authorities shall reject the tender, where they have established that the tender is abnormally low because it does not comply with applicable obligations referred to in Article 18(2).

4.

Where a contracting authority establishes that a tender is abnormally low because the tenderer has obtained State aid, the tender may be rejected on that ground alone only after consultation with the tenderer where the latter is unable to prove, within a sufficient time limit fixed by the contracting authority, that the aid in question was compatible with the internal market within the meaning of Article 107 TFEU. Where the contracting authority rejects a tender in those circumstances, it shall inform the Commission thereof.

5.

Upon request, Member States shall make available to other Member States by means of administrative cooperation any information at its disposal, such as laws, regulations, universally applicable collective agreements or national technical standards, relating to the evidence and documents produced in relation to details listed in paragraph 2.

The 10 that are cited most themselves, of 22.

  • Judgment of the Court (Fourth Chamber) of 15 September 2022. Veridos GmbH v Ministar na vatreshnite raboti na Republika Bulgaria and MühlbauDecision

    This request for a preliminary ruling concerns the interpretation of Articles 56 and 69 of Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing Directive 2004/18/EC (OJ …

    15 Sep 2022 · 62020CJ0669

  • Regulation (EU) 2022/2560Law

    … изгодна, включително като представят елементите, посочени в член 69, параграф 2 от Директива 2014/24/ЕС или в член 84, параграф 2 от …

  • Bundesvergabegesetz 2018359Law

    … einer sonstigen Vertragspartei des EWR-Abkommens oder der Schweizerischen Eidgenossenschaft im Zusammenhang mit den Art. 42, 43, 44, 57, 59, 60, 62, 64 und 69 der Richtlinie 2014/24/EU und den Art. 62, 81 und 84 der Richtlinie 2014/25/EU …

  • Judgment of the Court (Fourth Chamber) of 10 September 2020. Tax-Fin-Lex d.o.o. v Ministrstvo za notranje zadeve.Decision

    Accordingly, since a tender at a price of EUR 0.00 could be classified as an abnormally low tender within the meaning of Article 69 of Directive 2014/24, where a contracting authority is presented with such a tender, it must follow the …

    10 Sep 2020 · 62019CJ0367

  • Judgment of the Court (Fourth Chamber) of 14 January 2021. RTS infra BVBA and Aannemingsbedrijf Norré-Behaegel v Vlaams Gewest.Decision

    Article 69 of Directive 2014/24, entitled ‘Abnormally low tenders’, provides in paragraph 1: ‘Contracting authorities shall require economic operators to explain the price or costs proposed in the tender where tenders appear to be …

    14 Jan 2021 · 62019CJ0387

  • VwGH 03.09.2024, Ra 2021/04/0101Decision

    … Ein derartiges Vorbringen ist vom Bieter zu belegen (vgl. RV 69 BlgNR 26. GP, 154, unter Bezugnahme auf Art. 69 Abs. 2 der Richtlinie 2014/24/EU).

    3 Sep 2024 · JWT_2021040101_20240903L00

  • Opinion of Advocate General Campos Sánchez-Bordona delivered on 24 February 2022. Veridos GmbH v Ministar na vatreshnite raboti na RepublikaDecision

    Veridos appealed against the decision of 25 June 2020 before the Varhoven administrativen sad (Supreme Administrative Court, Bulgaria), which has referred the following questions to the Court of Justice for a preliminary ruling: Is Article …

    24 Feb 2022 · 62020CC0669

  • Opinion of Advocate General Campos Sánchez-Bordona delivered on 17 September 2020. RTS infra BVBA and Aannemingsbedrijf Norré-Behaegel v VlaDecision

    RTS-Norré proposes that Article 57(6) of Directive 2014/24 be interpreted by analogy with the rules governing abnormally low tenders (Article 69). The referring court also refers to that interpretative criterion in its order. [Order for …

    17 Sep 2020 · 62019CC0387

  • Regulation (EU) 2024/311083Law

    … за изключване на оферти с необичайно ниска стойност съгласно член 69 от Директива 2014/24/ЕС и член 84 от Директива 2014/25/ЕС. 7. За …

  • Regulation (EU) 2024/173525Law

    … възможността за изключване на необичайно ниски оферти съгласно член 69 от Директива 2014/24/ЕС и член 84 от Директива 2014/25/ЕС. в) членове …