Art. 55 Directive (EU) 2014/24

Informing candidates and tenderers

In forcesince 26 Feb 2014cited 14×
1.

Contracting authorities shall as soon as possible inform each candidate and tenderer of decisions reached concerning the conclusion of a framework agreement, the award of the contract or admittance to a dynamic purchasing system, including the grounds for any decision not to conclude a framework agreement, not to award a contract for which there has been a call for competition, to recommence the procedure or not to implement a dynamic purchasing system.

2.

On request from the candidate or tenderer concerned, the contracting authority shall as quickly as possible, and in any event within 15 days from receipt of a written request, inform:

(a)

any unsuccessful candidate of the reasons for the rejection of its request to participate,

(b)

any unsuccessful tenderer of the reasons for the rejection of its tender, including, for the cases referred to in Article 42(5) and (6), the reasons for its decision of non-equivalence or its decision that the works, supplies or services do not meet the performance or functional requirements,

(c)

any tenderer that has made an admissible tender of the characteristics and relative advantages of the tender selected as well as the name of the successful tenderer or the parties to the framework agreement,

(d)

any tenderer that has made an admissible tender of the conduct and progress of negotiations and dialogue with tenderers.

3.

Contracting authorities may decide to withhold certain information referred to in paragraphs 1 and 2, regarding the contract award, the conclusion of framework agreements or admittance to a dynamic purchasing system, where the release of such information would impede law enforcement or would otherwise be contrary to the public interest, would prejudice the legitimate commercial interests of a particular economic operator, whether public or private, or might prejudice fair competition between economic operators.

The 10 that are cited most themselves, of 14.

  • Directive (EU) 2014/2346Law

    … със следното: „— обобщение на съответните причини съгласно член 55, параграф 2 от Директива 2014/24/ЕС, при спазване на член 55, параграф …

  • Judgment of the Court (Grand Chamber) of 7 September 2021. 'Klaipėdos regiono atliekų tvarkymo centras' v UAB.Decision

    Under Article 21(1) of Directive 2014/24, unless otherwise provided in that directive or in the national law to which the contracting authority is subject, in particular legislation concerning access to information, and without prejudice …

    7 Sep 2021 · 62019CJ0927

  • Directive (EU) 1989/6652a2fLaw

    … се придружава от: обобщение на съответните причини съгласно член 55, параграф 2 от Директива 2014/24/ЕС, при спазване на член 55, параграф …

  • Opinion of Advocate General Campos Sánchez-Bordona delivered on 15 April 2021. 'Klaipėdos regiono atliekų tvarkymo centras' v UAB.Decision

    Directive 2014/24 brings together several rules relating to the publication of information held by the contracting authority. These include [Directive 2014/24 contains other provisions on the protection of confidentiality, to which I shall …

    15 Apr 2021 · 62019CC0927

  • Judgment of the Court (Grand Chamber) of 21 December 2023. Infraestruturas de Portugal, SA and Futrifer Indústrias Ferroviárias, SA v TosccaDecision

    Article 55 of that directive, entitled ‘Informing candidates and tenderers’, provides, in paragraph 2(b) thereof: ‘On request from the candidate or tenderer concerned, the contracting authority shall as quickly as possible, and in …

    21 Dec 2023 · 62022CJ0066

  • Judgment of the Court (Fourth Chamber) of 17 November 2022. Antea Polsk S.A., 'Pectore-Eco'' sp. z o.o., Instytut Ochrony Środowiska - PaństDecisioninterprets

    However, if the effectiveness of EU law is not to be undermined, the Member States, when exercising the discretion conferred on them by Article 21(1) of that directive, must refrain from introducing regimes which do not ensure full respect …

    17 Nov 2022 · 62021CJ0054

  • Judgment of the Court (Eighth Chamber) of 14 July 2022. EPIC Financial Consulting Ges.m.b.H. v Republik Österreich and Bundesbeschaffung GmbDecision

    … се придружава от: обобщение на съответните причини съгласно член 55, параграф 2 от Директива [2014/24], при спазване на член 55, параграф 3 …

    14 Jul 2022 · 62021CJ0274

  • Judgment of the Court (Tenth Chamber) of 8 December 2022. AAS „BTA Baltic Insurance Company” v Iepirkumu uzraudzības birojs and Tieslietu miDecision

    In that regard, it should be recalled at the outset that, as is apparent from the case-law of the Court, EU law does not preclude Member States from providing for the possibility, referred to in Article 55(1) of Directive 2014/24, of …

    8 Dec 2022 · 62021CJ0769

  • Opinion of Advocate General Campos Sánchez-Bordona delivered on 11 May 2023. Infraestruturas de Portugal, SA and Futrifer Indústrias FerroviDecision

    … transposition effected by the Portuguese provisions was not entirely consistent with that directive: in particular, Article 55(1)(f) of the CCP improperly curtails the contracting authority’s discretion to exclude tenderers involved in …

    11 May 2023 · 62022CC0066

  • Cour administrative, 23.03.2023, n° 48300C du rôleDecision

    Après une interprétation de l’article 97 du règlement grand-ducal du 8 avril 2018 « à la lumière de l’article 55 de la directive 2014/24/UE et de la jurisprudence de la CJUE » tendant à dégager le degré de précision que doit …

    23 Mar 2023 · 48300C