62 4. ASSESSMENT › 4.3. ASSESSMENT OF THE DEROGATION REQUESTED FROM CHAPTER III › 4.3.4. The derogation for the authorisation of refurbishing, upgrading and expanding existing capacity can be granted, Decision_act (EU) 2014/536

In forcesince 14 Aug 2014

Moreover, in case the derogation is granted directly to PPC, it is important that the terms stipulate the obligations as regards the time by which the authorised conventional power plant must be fully operational and include provisions ensuring full and effective compliance with such obligations. Upon expiry, on RAE's sole discretion, such direct authorisation can be prolonged but only if it expired for reasons fully beyond the control of PPC. Upon expiry, RAE should organise an authorisation procedure in full compliance with Article 7(1) of Directive 2009/72/EC, thus including the participation of third parties.