Art. 4 Decision_act (EU) 2014/489

In forcesince 19 Jun 2013cited 2×
1.

Recovery of the aid granted under the scheme referred to in Article 1 shall be immediate and effective.

2.

Spain shall ensure that this Decision is implemented within four months following the date of notification thereof.

3.

Within two months following notification of this Decision, Spain shall submit the following information to the Commission:

(a)

the list of beneficiaries that have received aid under the scheme referred to in Article 1 and the total amount of aid received by each of them under that scheme, broken down by the categories indicated in section 6.2 above;

(b)

the total amount (principal and recovery interests) to be recovered from each beneficiary;

(c)

a detailed description of the measures already taken and planned in order to comply with this Decision;

(d)

documents demonstrating that the beneficiaries have been ordered to repay the aid.

4.

Spain shall keep the Commission informed of the progress of the national measures taken to implement this Decision until recovery of the aid granted under the scheme referred to in Article 1 has been completed. It shall immediately submit, at the Commission's request, information on the measures already taken and planned in order to comply with this Decision. It shall also provide detailed information concerning the amounts of aid and interest already recovered from the beneficiaries.

  • Judgment of the Court (Fourth Chamber) of 20 December 2017. Comunidad Autónoma de Galicia and Redes de Telecomunicación Galegas Retegal, SA Decision

    It follows, in that respect, from paragraph 153 of the judgment under appeal that the General Court, inter alia, addressed the appellants’ arguments by noting that, in recitals 189 to 195 of the decision at issue, set out in section 6.2 …

    20 Dec 2017 · 62016CJ0070

  • Judgment of the General Court (Fifth Chamber) of 26 November 2015. Kingdom of Spain v European Commission.Decision

    As regards the Kingdom of Spain’s argument that the Commission did not justify the extrapolation method used in order to arrive at the conclusion that most of the calls for tenders were not technologically neutral, it should be observed …

    26 Nov 2015 · 62013TJ0461