Art. 101 Regulation (EU) No 1303/2013 of the European Parliament and of the Council of 17 Decembe…

Information necessary for the approval of a major project

In forcesince 17 Dec 2013cited 10×

Before a major project is approved, the managing authority shall ensure that the following information is available:

(a)

details concerning the body to be responsible for implementation of the major project, and its capacity;

(b)

a description of the investment and its location;

(c)

the total cost and total eligible cost, taking account of the requirements set out in Article 61;

(d)

feasibility studies carried out, including the options analysis, and the results;

(e)

a cost-benefit analysis, including an economic and a financial analysis, and a risk assessment;

(f)

an analysis of the environmental impact, taking into account climate change adaptation and mitigation needs, and disaster resilience;

(g)

an explanation as to how the major project is consistent with the relevant priority axes of the operational programme or operational programmes concerned, and its expected contribution to achieving the specific objectives of those priority axes and the expected contribution to socio-economic development;

(h)

the financing plan showing the total planned financial resources and the planned support from the Funds, the EIB, and all other sources of financing, together with physical and financial indicators for monitoring progress, taking account of the identified risks;

(i)

the timetable for implementing the major project and, where the implementation period is expected to be longer than the programming period, the phases for which support from the Funds is requested during the programming period.

The Commission shall adopt implementing acts establishing the methodology to be used based on recognised best practices, in carrying out the cost-benefit analysis referred to in point (e) of the first paragraph. Those implementing acts shall be adopted in accordance with the advisory procedure referred to in Article 150(2).

At the initiative of a Member State, the information in points (a) to (i) of the first paragraph may be assessed by independent experts supported by technical assistance of the Commission or, in agreement with the Commission, by other independent experts ("quality review"). In other cases, the Member State shall submit to the Commission the information set out in points (a) to (i) of the first paragraph as soon as it is available.

The Commission shall be empowered to adopt delegated acts, in accordance with Article 149, laying down the methodology to be used in carrying out the quality review of a major project.

The Commission shall adopt implementing acts establishing the format for submission of the information set out in points (a) to (i) of the first paragraph. Those implementing acts shall be adopted in accordance with the advisory procedure referred to in Article 150(2).

  • Commission Delegated Regulation (EU) No 480/2014 of 3 March 2014 supplementing Regulatio…2223Law

    … 320.], and in particular Articles 22(7), 37(13), 38(4), 40(4), 41(3), 42(1), 42(6), 61(3), 68(1), 101, 125(8), 125(9), 127(7), 127(8) and 144(6) thereof, Whereas:

  • Commission Implementing Regulation (EU) No 1011/2014 of 22 September 2014 laying down de…Law

    … qui convient et compléter les données sur la base du format de présentation des informations énoncées à l'article 101 du règlement (UE) no 1303/2013. Méthode de calcul des recettes nettes potentielles | Cochez une seule case Calcul …

  • Judgment of the General Court (Seventh Chamber) of 1 March 2018 (Extracts). Republic of Poland v European Commission.Decision

    With regard to the second line of argument, it must be noted that Regulation No 1303/2013 does not apply to the present case, since Article 152(1) thereof provides that Regulation No 1083/2006 is to continue to apply to assistance and …

    1 Mar 2018 · 62015TJ0402

  • Regulation (EU) 2015/20723Law

    … documents préparés pour le grand projet, notamment ceux qui contiennent les autres informations mentionnées à l'article 101, paragraphe 1, du règlement (UE) no 1303/2013. 1.3. L'ACA doit obéir aux principes suivants: l'ACA doit être …

  • Arrêt du Tribunal (septième chambre) du 14 février 2019. République de Pologne contre Commission européenne.Decision

    Quant au second argument, il convient d’observer que le règlement n o 1303/2013 ne trouve pas application en l’espèce, dans la mesure où son article 152, paragraphe 1, dispose que le règlement n o 1083/2006 continue à …

    14 Feb 2019 · 62017TJ0366

  • Arrêt du Tribunal (septième chambre) du 1er mars 2018. République de Pologne contre Commission européenne.Decision

    La conclusion retenue au point 110 ci-dessus, de surcroît, est corroborée, a contrario, par la nouvelle procédure d’approbation tacite prévue à l’article 102, paragraphe 1, deuxième alinéa, du règlement (UE) n o 1303/2013 du …

    1 Mar 2018 · 62015TJ0316

  • Judgment of the General Court (Seventh Chamber) of 22 June 2022. Italian Republic v European Commission.Decision

    In that context, Article 102 of Regulation No 1303/2013 requires the Commission, in order to determine whether the selection of the major project by the management authority is justified, to evaluate the major project on the basis of …

    22 Jun 2022 · 62019TJ0357

  • Regulation (EU) 2019/256Law

    … 1083/2006 [ΕΕ L 347 της 20.12.2013, σ. 320.], και ιδίως το άρθρο 101 πέμπτο εδάφιο, το άρθρο 106 δεύτερο εδάφιο και το άρθρο 111 παράγραφος 5, Έχοντας …

  • Commission Implementing Regulation (EU) No 1011/2014 of 22 September 2014 laying down de…Law

    … C.1. Please complete table below on the basis of the format for submission of information set out in accordance with Article 101 of Regulation (EU) No 1303/2013. EUR | Total Project costs(A) | Ineligible costs(B) | Eligible costs(C) = (A) …

  • Commission Delegated Regulation (EU) No 480/2014 of 3 March 2014 supplementing Regulatio…2223Law

    1. Quality review criteria for the information requirements of Article 101(a) of Regulation (EU) No 1303/2013 of the European Parliament and of the Council Evidence of sufficient technical, legal, financial and administrative capacity to …