13 2. DESCRIPTION OF THE AID › 2.2. THE iTiden PROJECT [Most of the information in this Section is taken from the iTiden website (www.itiden.ax), complemented by information (consistent with the public information) submitted by the Finnish authorities.], Decision_act (EU) 2012/252

In forcesince 13 Jul 2011

At the beginning of 2002 a working group for the building of iTiden was appointed and an architect commissioned. Potential tenants were sounded out for their interest in renting property in iTiden. The preparatory land works were carried out in the spring of 2003 and the construction of phase 1 (the project was designed in two consecutive construction phases) started in the summer of 2003. The first tenants moved into the completed ‘phase 1’ part of iTiden on 1 December 2004.