123 8. RECOVERY OF THE AID › 8.1. FINLAND’S ARGUMENTS, Decision_act (EU) 2012/252

In forcesince 13 Jul 2011

Concerning the loan guarantees, the Commission has shown that the guarantee scheme had been substantively altered even before the granting of the guarantees at issue in this decision. These alterations, made by the Åland authorities, have not been notified to the Commission. The consequence is that any guarantees granted under the national rules that made up the original scheme have to be considered new aid. It is well-established that no beneficiary of aid can legitimately expect that aid that should have been notified to the Commission under Article 108 TFEU but has not been so, is lawful [See case C-24/95 Land Rheinland-Pfalz v Alcan Deutschland GmbH, judgment of 20.3.1997, [1997] ECR I-1591, paragraph 49.].