Art. 6 Directive (EU) 2011/92

In forcesince 15 May 2014cited 86×
1.

Member States shall take the measures necessary to ensure that the authorities likely to be concerned by the project by reason of their specific environmental responsibilities or local and regional competences are given an opportunity to express their opinion on the information supplied by the developer and on the request for development consent, taking into account, where appropriate, the cases referred to in Article 8a(3). To that end, Member States shall designate the authorities to be consulted, either in general terms or on a case-by-case basis. The information gathered pursuant to Article 5 shall be forwarded to those authorities. Detailed arrangements for consultation shall be laid down by the Member States.

2.

In order to ensure the effective participation of the public concerned in the decision-making procedures, the public shall be informed electronically and by public notices or by other appropriate means, of the following matters early in the environmental decision-making procedures referred to in Article 2(2) and, at the latest, as soon as information can reasonably be provided:

(a)

the request for development consent;

(b)

the fact that the project is subject to an environmental impact assessment procedure and, where relevant, the fact that Article 7 applies;

(c)

details of the competent authorities responsible for taking the decision, those from which relevant information can be obtained, those to which comments or questions can be submitted, and details of the time schedule for transmitting comments or questions;

(d)

the nature of possible decisions or, where there is one, the draft decision;

(e)

an indication of the availability of the information gathered pursuant to Article 5;

(f)

an indication of the times and places at which, and the means by which, the relevant information will be made available;

(g)

details of the arrangements for public participation made pursuant to paragraph 5 of this Article.

3.

Member States shall ensure that, within reasonable time-frames, the following is made available to the public concerned:

(a)

any information gathered pursuant to Article 5;

(b)

in accordance with national legislation, the main reports and advice issued to the competent authority or authorities at the time when the public concerned is informed in accordance with paragraph 2 of this Article;

(c)

in accordance with the provisions of Directive 2003/4/EC of the European Parliament and of the Council of 28 January 2003 on public access to environmental information [OJ L 41, 14.2.2003, p. 26.], information other than that referred to in paragraph 2 of this Article which is relevant for the decision in accordance with Article 8 of this Directive and which only becomes available after the time the public concerned was informed in accordance with paragraph 2 of this Article.

4.

The public concerned shall be given early and effective opportunities to participate in the environmental decision-making procedures referred to in Article 2(2) and shall, for that purpose, be entitled to express comments and opinions when all options are open to the competent authority or authorities before the decision on the request for development consent is taken.

5.

The detailed arrangements for informing the public, for example by bill posting within a certain radius or publication in local newspapers, and for consulting the public concerned, for example by written submissions or by way of a public inquiry, shall be determined by the Member States. Member States shall take the necessary measures to ensure that the relevant information is electronically accessible to the public, through at least a central portal or easily accessible points of access, at the appropriate administrative level.

6.

Reasonable time-frames for the different phases shall be provided for, allowing sufficient time for:

(a)

informing the authorities referred to in paragraph 1 and the public; and

(b)

the authorities referred to in paragraph 1 and the public concerned to prepare and participate effectively in the environmental decision-making, subject to the provisions of this Article.

7.

The time-frames for consulting the public concerned on the environmental impact assessment report referred to in Article 5(1) shall not be shorter than 30 days.

The 10 that are cited most themselves, of 86.

  • Directive (EU) 2014/52Lawamends

  • Judgment of the Court (Fifth Chamber) of 16 April 2015. Karoline Gruber v Unabhängiger Verwaltungssenat für Kärnten and Others.Decision

    Although it is possible to integrate the EIA procedure into another administrative procedure, it is important that, as the Advocate General pointed out in points 57 and 58 of her Opinion, all the requirements of Articles 5 to 10 of …

    16 Apr 2015 · 62013CJ0570

  • Judgment of the Court (First Chamber) of 28 May 2020. IL and Others v Land Nordrhein-Westfalen.Decisioninterprets

    In that context, it would be necessary to answer the question whether the documents made available to the public under Article 6 of Directive 2011/92 must systematically include a report on compliance with the legislation on water quality. …

    28 May 2020 · 62018CJ0535

  • Conseil d'État, 6ème - 1ère chambres réunies, 06/12/2017, 400559Decision

    … préjudicielle portant sur l'interprétation de l'article 3 de la directive 2001/42/CE du 27 juin 2001 ainsi que des articles 4 et 6 de la directive 2011/92/UE du 13 décembre 2011 ;

    6 Dec 2017 · CETATEXT000036211336

  • Judgment of the Court (Grand Chamber) of 29 July 2019. Inter-Environnement Wallonie ASBL and Bond Beter Leefmilieu Vlaanderen ASBL v ConseilDecision

    In those circumstances, the Cour constitutionnelle (Constitutional Court) decided to stay the proceedings and to refer the following questions to the Court of Justice for a preliminary ruling: Must Article 2(1) to (3), (6) and (7), Article …

    29 Jul 2019 · 62017CJ0411

  • BVerwG, Urteil vom 28. November 2017 - 7 A 17/12Decision

    … Art. 6 Abs. 2 bis 6 der Richtlinie 2011/92/EU). Über die Gewährleistung eines Beteiligungs- und Mitwirkungsrechts gehen die Regelungen nicht hinaus.

    28 Nov 2017 · WBRE201800316

  • BVerwG, Urteil vom 25. März 2015 - 9 A 1/14Decision

    … 1 UVPG noch Art. 6 der Richtlinie 2011/92/EU des Europäischen Parlaments und des Rates vom 13. Dezember 2011 über die Umweltverträglichkeitsprüfung bei bestimmten öffentlichen und privaten Projekten - UVP-Richtlinie - bzw. Art. 8 des …

    25 Mar 2015 · WBRE201500247

  • Judgment of the Court (Second Chamber) of 7 June 2018. Inter-Environnement Bruxelles ASBL and Others v Région de Bruxelles-Capitale.Decision

    Pursuant to Article 4(2) of Directive 2011/92 (‘the EIA Directive’), the Member States are to determine whether the projects listed in Annex II to that directive are to be made subject to an assessment in accordance with Articles 5 to …

    7 Jun 2018 · 62016CJ0671

  • BVerwG, Urteil vom 28. November 2017 - 7 A 1/17 u.a.Decision

    … Art. 6 Abs. 2 bis 6 der Richtlinie 2011/92/EU). Über die Gewährleistung eines Beteiligungs- und Mitwirkungsrechts gehen die Regelungen nicht hinaus.

    28 Nov 2017 · WBRE201800358

  • Judgment of the Court (Third Chamber) of 24 February 2022. Namur-Est Environnement ASBL v Région wallonne.Decisioninterprets

    This request for a preliminary ruling concerns the interpretation of Articles 1, 2 and 5 to 8 of Directive 2011/92/EU of the European Parliament and of the Council of 13 December 2011 on the assessment of the effects of certain public and …

    24 Feb 2022 · 62020CJ0463