Art. 3 Directive (EU) 2011/7

Transactions between undertakings

In forcesince 16 Feb 2011cited 31×
1.

Member States shall ensure that, in commercial transactions between undertakings, the creditor is entitled to interest for late payment without the necessity of a reminder, where the following conditions are satisfied:

(a)

the creditor has fulfilled its contractual and legal obligations; and

(b)

the creditor has not received the amount due on time, unless the debtor is not responsible for the delay.

2.

Member States shall ensure that the applicable reference rate:

(a)

for the first semester of the year concerned shall be the rate in force on 1 January of that year;

(b)

for the second semester of the year concerned shall be the rate in force on 1 July of that year.

3.

Where the conditions set out in paragraph 1 are satisfied, Member States shall ensure the following:

(a)

that the creditor is entitled to interest for late payment from the day following the date or the end of the period for payment fixed in the contract;

(b)

where the date or period for payment is not fixed in the contract, that the creditor is entitled to interest for late payment upon the expiry of any of the following time limits:

(i)

30 calendar days following the date of receipt by the debtor of the invoice or an equivalent request for payment;

(ii)

where the date of the receipt of the invoice or the equivalent request for payment is uncertain, 30 calendar days after the date of receipt of the goods or services;

(iii)

where the debtor receives the invoice or the equivalent request for payment earlier than the goods or the services, 30 calendar days after the date of the receipt of the goods or services;

(iv)

where a procedure of acceptance or verification, by which the conformity of the goods or services with the contract is to be ascertained, is provided for by statute or in the contract and if the debtor receives the invoice or the equivalent request for payment earlier or on the date on which such acceptance or verification takes place, 30 calendar days after that date.

4.

Where a procedure of acceptance or verification, by which the conformity of the goods or services with the contract is to be ascertained, is provided for, Member States shall ensure that the maximum duration of that procedure does not exceed 30 calendar days from the date of receipt of the goods or services, unless otherwise expressly agreed in the contract and provided it is not grossly unfair to the creditor within the meaning of Article 7.

5.

Member States shall ensure that the period for payment fixed in the contract does not exceed 60 calendar days, unless otherwise expressly agreed in the contract and provided it is not grossly unfair to the creditor within the meaning of Article 7.

The 10 that are cited most themselves, of 31.

  • Judgment of the Court (Third Chamber) of 20 October 2022. BFF Finance Iberia S.A.U v Gerencia Regional de Salud de la Junta de Castilla y LeDecision

    The right to ‘reasonable’ compensation provided for in Article 6(3) of Directive 2011/7 ‘for any recovery costs exceeding that fixed sum and incurred due to the debtor’s late payment’ covers recovery costs, whatever they may be, …

    20 Oct 2022 · 62020CJ0585

  • Judgment of the Court (Ninth Chamber) of 9 July 2020. RL sp. z o.o. v J.M.Decisioninterprets

    It should be noted, secondly, that, in commercial transactions between undertakings, the interest for late payment provided for in Article 3 of Directive 2011/7 is payable when the conditions laid down in Article 3(1) thereof are …

    9 Jul 2020 · 62019CJ0199

  • Judgment of the Court (Ninth Chamber) of 13 January 2022. Skarb Państwa - Starosta Nyski v New Media Development & Hotel Services Sp. z o.o.Decision

    It should also be observed that Article 3 of Directive 2011/7 relates only to transactions between undertakings. As is clear from paragraph 36 of this judgment, the way in which the concept of an ‘undertaking’ is defined in that …

    13 Jan 2022 · 62020CJ0327

  • Judgment of the Court (Grand Chamber) of 28 January 2020. European Commission v Italian Republic.Decision

    It should therefore be noted that the wording of Article 3 of that directive, which relates to transactions between undertakings, differs significantly from that of Article 4 of the directive, which relates to transactions between …

    28 Jan 2020 · 62018CJ0122

  • Judgment of the Court (Ninth Chamber) of 13 September 2018. Česká pojišťovna a.s. v WCZ spol. s r.o.Decision

    In those circumstances, the Okresní soud v Českých Budějovicích (České Budějovice District Court, Czech Republic) decided to stay the proceedings and to refer the following question to the Court for a preliminary ruling: ‘Must …

    13 Sep 2018 · 62017CJ0287

  • Judgment of the Court (Ninth Chamber) of 1 June 2017. Piotr Zarski v Andrzej Stadnicki.Decision

    This request for a preliminary ruling concerns the interpretation of Article 1(1), Article 2(1), Article 3, Article 6, Article 8 and Article 12(4) of Directive 2011/7/EU of the European Parliament and of the Council of 16 February 2011 on …

    1 Jun 2017 · 62016CJ0330

  • Judgment of the Court (Eighth Chamber) of 4 May 2023. ALD Automotive s.r.o. v DY.Decisioninterprets

    By its first question, the referring court asks, in essence, whether Article 6(1) of Directive 2011/7, read in conjunction with Article 3 thereof, must be interpreted as meaning that, where a single contract provides for periodic payments, …

    4 May 2023 · 62022CJ0078

  • Judgment of the Court (Eighth Chamber) of 1 December 2022. DOMUS-SOFTWARE-AG v Marc Braschoß Immobilien GmbH.Decisioninterprets

    This request for a preliminary ruling concerns the interpretation of Article 6(1) and (2), read in conjunction with Article 3, of Directive 2011/7/EU of the European Parliament and of the Council of 16 February 2011 on combating late …

    1 Dec 2022 · 62021CJ0370

  • Judgment of the Court (Tenth Chamber) of 20 October 2022. A Oy v B Ky and Joint heirs of C.Decision

    Like Directive 2000/35, Directive 2011/7 lays down only certain rules in this area, which include those relating to interest for late payment and to compensation for recovery costs (see, to that effect, judgment of 16 February 2017, IOS …

    20 Oct 2022 · 62021CJ0406

  • Opinion of Advocate General Rantos delivered on 28 April 2022. BFF Finance Iberia S.A.U v Gerencia Regional de Salud de la Junta de CastillaDecision

    As a preliminary point, I note that Article 6 of Directive 2011/7 seeks to ensure a minimum compensation for the recovery costs incurred by the creditor where interest for late payment becomes payable under that directive, in accordance …

    28 Apr 2022 · 62020CC0585