For the purposes of this Regulation, the following definitions shall apply:
‘carbon capture and storage’ means the capture of carbon dioxide (CO2) from industrial installations, its transport to a storage site and its injection into a suitable underground geological formation for the purposes of permanent storage;
‘eligible costs’ has the same meaning as in Regulation (EC, Euratom) No 2342/2002;
‘gas and electricity infrastructures’ means:
all high-voltage lines, excluding those of distribution networks, and submarine links, provided that this infrastructure is used for interregional or international transmission or connection;
high-pressure gas pipelines, excluding those of distribution networks;
underground storage facilities connected to the high-pressure gas pipelines referred to in point (ii);
reception, storage and regasification facilities for liquefied natural gas (LNG); and
any equipment or installations essential for the infrastructure referred to in points (i), (ii), (iii) or (iv) to operate properly, including protection, monitoring and control systems;
‘part of a project’ means any activity that is independent financially, technically or over time and which contributes to the completion of a project;
‘investment phase’ means the phase of a project during which construction takes place and capital costs are incurred;
‘offshore wind energy’ means the electric power generated from turbine engines powered by wind and situated in the sea, whether near or far from the shore;
‘planning phase’ means the phase of a project that precedes the investment phase, during which project implementation is prepared, and includes, where appropriate, feasibility assessment, preparatory and technical studies, obtaining licences and authorisations and incurring capital costs.