1.

Member States shall submit to the Commission by 1 March each year, a report on the implementation of the measures provided for in their support programmes referred to in Section 4 of Chapter II of Title I of Part II of Regulation (EU) No 1308/2013 of the European Parliament and of the Council [Regulation (EU) No 1308/2013 of the European Parliament and of the Council of 17 December 2013 establishing a common organisation of the markets in agricultural products and repealing Council Regulations (EEC) No 922/72, (EEC) No 234/79, (EC) No 1037/2001 and (EC) No 1234/2007 (OJ L 347, 20.12.2013, p. 671).] during the previous financial year.

Those reports shall list and describe the measures for which Union assistance under the support programmes was granted.

Those reports shall be presented by Member States to the Commission in the form set out in Annexes V and VI to this Regulation. The information contained in the appropriate tables shall refer to each year in respect of the measures of the support programme:

(a)

a statement of expenditure by financial year already incurred in the programming period which will in no cases overshoot the budgetary limit for the Member State as laid down in Annex VI to Regulation (EU) No 1308/2013;

(b)

forecasts for subsequent financial years until the end of the planned period of implementation of the support programme, up to the budgetary limit for the Member State as laid down in VI to Regulation (EU) No 1308/2013 and in coherence with the most updated submission sent in accordance with Article 3 of this Regulation.

2.

In the same communication, technical data related to the implementation of the measures in the support programme, shall be presented by the Member States in the form set out in Annex VII. The details on the implementation of the promotion measure shall be presented by the Member States in the form set out in Annex VIII.

3.

References to a given financial year shall refer to payments actually made by Member States between 16 October and 15 October of the following year.

4.

Member States shall, by 1 March 2014 and, a second time, by 1 March 2017, submit to the Commission an evaluation of the costs and benefits of the support programmes as well as an indication of how to increase their efficiency.

Those evaluations shall be presented by the Member States to the Commission in the form set out in Annexes V and VI. In addition the following items shall be inserted in the conclusions:

—C1Evaluation of the costs and benefits of the support programme,

—C2Ways to increase the efficiency of the support programme.

5.

Member States shall communicate to the Commission the measures taken to comply with the provisions foreseen in Article 9(1) and 12(1)(d). The communication shall be made in the form set out in Annexes VIIIa and VIIIb.

6.

Member States deciding to transfer, for 2014 and from 2015 onwards, the entire amount of their national envelope for the support programmes in order to increase their national ceilings for direct payments referred to in Article 40 of Regulation (EC) No 73/2009, shall not be required to submit the forms set out in Annexes V to VIIIc to this Regulation.

7.

Member States shall record the details of all support programmes, whether or not amended, and of all measures carried out in pursuance of programmes.