Art. 47 Commission Regulation (EC) No 718/2007 of 12 June 2007 implementing Council Regulation (…

Closure of a programme

In forcesince 30 Jan 2010cited 1×
1.

After an application for final payment has been received by the Commission, a programme is considered closed as soon as one of the following occurs:

payment of the final balance due by the Commission,

issuance of a recovery order by the Commission,

de-commitment of the final balance of the budgetary commitment by the Commission.

2.

The closure of a programme does not prejudice the Commission's right to undertake a financial correction at a later stage.

3.

The closure of a programme does not affect the obligations of the beneficiary country to continue to retain related documents, in accordance with Article 48.