1.

The competent authorities of destination which have jurisdiction over specific recovery facilities may decide to issue pre-consents to such facilities.

Such decisions shall be limited to a specific period and may be revoked at any time.

2.

In the case of a general notification submitted in accordance with Article 13, the period of validity of the consent referred to in Article 9(4) and (5) may be extended to up to three years by the competent authority of destination in agreement with the other competent authorities concerned.

3.

Competent authorities which decide to issue a pre-consent to a facility in accordance with paragraphs 1 and 2 shall inform the Commission and, where appropriate, the OECD Secretariat of:

(a)

the name, registration number and address of the recovery facility;

(b)

the description of technologies employed, including R-code(s);

(c)

the wastes as listed in Annexes IV and IVA or the wastes to which the decision applies;

(d)

the total pre-consented quantity;

(e)

the period of validity;

(f)

any change in the pre-consent;

(g)

any change in the information notified; and

(h)

any revocation of the pre-consent.

For this purpose the form set out in Annex VI shall be used.

4.

By way of derogation from Articles 9, 10 and 12, the consent given in accordance with Article 9, conditions imposed in accordance with Article 10 or objections raised in accordance with Article 12 by the competent authorities concerned shall be subject to a time limit of seven working days following the date of transmission of the acknowledgement of the competent authority of destination in accordance with Article 8.

5.

Notwithstanding paragraph 4, the competent authority of dispatch may decide that more time is needed in order to receive further information or documentation from the notifier.

In such cases, the competent authority shall, within seven working days, inform the notifier in writing with copies to the other competent authorities concerned.

The total time needed shall not exceed 30 days following the date of transmission of the acknowledgement of the competent authority of destination in accordance with Article 8.

  • Regulation (EU) 2024/115785Law

    … Издадено предварително съгласие за съоръжение в съответствие с член 14 от Регламент (ЕО) № 1013/2006 престава да бъде валидно не …

  • Judgment of the Court (Grand Chamber) of 8 September 2009. Commission of the European Communities v European Parliament and Council of the EDecision

    Title II of the contested regulation, which comprises Articles 3 to 32 thereof, concerns shipments of waste within the Community with or without transit through third countries. That title provides for the basic scheme under that …

    8 Sep 2009 · 62006CJ0411

  • Judgment of the Court (Grand Chamber) of 21 January 2025. Land Niedersachsen v Conti 11. Container Schiffahrts-GmbH & Co. KG MS 'MSC FlaminiDecision

    Chapter 1 of Title II of Regulation No 1013/2006, which comprises Articles 4 to 17, describes the prior written notification and consent procedure.

    21 Jan 2025 · 62023CJ0188

  • Opinion of Advocate General Saugmandsgaard Øe delivered on 24 January 2019. ReFood GmbH & Co. KG v Landwirtschaftskammer Niedersachsen.Decision

    That reasoning does not, in my opinion, justify a different interpretation of Article 1(3)(d) of Regulation No 1013/2006 than that described thus far, since Regulation No 1069/2009 subjects to the more stringent provisions of Regulation No …

    24 Jan 2019 · 62017CC0634

  • Regulation (EU) 2025/129026Law

    … за които са издали предварително съгласие в съответствие с член 14, параграф 1 от Регламент (ЕО) № 1013/2006 на Европейския парламент и …

  • Opinion of Advocate General Ćapeta delivered on 16 May 2024. Land Niedersachsen v Conti 11. Container Schiffahrts-GmbH & Co. KG MS 'MSC FlamDecision

    Articles 4 to 17 of the Waste Shipments Regulation govern in detail the procedure of prior written notification and consent that must be followed both when the waste is shipped for disposal or for recovery operations.

    16 May 2024 · 62023CC0188

  • Opinion of Advocate General Rantos delivered on 17 June 2021. Regione Veneto v Plan Eco Srl.Decision

    Title II of that regulation, entitled ‘Shipments within the [European Union] with or without transit through third countries’, comprises, inter alia, Articles 3 to 32. Article 3 of that regulation, entitled ‘Overall procedural …

    17 Jun 2021 · 62020CC0315