Art. 9 Directive (EU) 2004/54

Tunnels whose design has not yet been approved

In forcesince 7 Aug 2009
1.

Any tunnel whose design has not been approved by the responsible authority by 1 May 2006 shall be subject to the requirements of this Directive.

2.

The tunnel shall be commissioned in accordance with the procedure laid down in Annex II.

Changed on 7 Aug 2009

1. Any runneltunnel whose design has not been approved by the responsible authority by [...] [24 months after the date of entry into force of this Directive.] 1 May 2006 shall be subject to the requirements of this Directive.

  1. 7 Aug 2009 – todayin force
  2. 29 Apr 2004 – 7 Aug 2009earlier wording