The "evergreen" supply contract with BSN which dated from 18 June 1981 required BSN to purchase from Solvay annually a quantity of 300000 tonnes ± 15 % for its glass factories in France. BSN's total soda ash requirement from 1982 to 1984 was in reality some 300000 tonnes, falling from 1985 onwards to around 270000 tonnes to 280000 tonnes annually. The minimum tonnage which BSN was obliged to purchase from Solvay under the terms of the 1981 agreement was 265000 tonnes, a tonnage which was not far short of its total requirements. The contract was of indefinite duration and continued for a period of two years after notice of termination either side. Solvay was the virtually exclusive supplier of soda ash to BSN from 1982 onwards, supplying each year some 98 % of its requirements.
Recital 99, Decision_act (EU) 2003/6
In forcesince 13 Dec 2000