In February and March 2001 Eurodiol was using [20 % to 40 %]* of capacity available of NMP production. BASF predicts that by 2003 it will produce [20 kt to 35 kt/a]* at the Feluy plant, which is equivalent to full capacity. Given the production processes at Eurodiol, if operated efficiently, BASF should be able to produce NMP more cheaply at Eurodiol after the merger than at its other plant. [...]*. It is therefore possible that BASF would concentrate on the BDO-related products at the Feluy plant and BDO production at Ludwigshafen. [...]*. However, irrespective of its future plans BASF would by acquiring a different technology become more flexible to respond to changes in demand of BDO and BDO-related products.
Recital 110, Decision_act (EU) 2002/365
In forcesince 11 Jul 2001