Recital 22, Decision_act (EU) 2001/695

In force

Germany had so far provided only a general restructuring plan (Grobkonzept) in which only a few operational measures were clearly defined. It was therefore impossible to assess the planned measures and the extent to which they were likely to overcome the structural deficiencies causing the problems. Moreover, the Commission could not establish a clear link between the operational part of the restructuring plan and the financial measures because the notification contained no details of the costs of the planned restructuring measures.