Recital 23, Decision_act (EU) 2001/162

In force

The mean production cost in 1998, at 1992 prices, of the undertakings receiving aid under Article 3 of Decision No 3632/93/ECSC is ECU 87,7/tce, broken down as follows:

–

10 % of production at costs between ECU 20 and 60/tce,

–

50 % of production at costs between ECU 60 and 80/tce,

–

30 % of production at costs between ECU 80 and 95/tce,

–

10 % of production at costs between ECU 95 and 199/tce.

  • celex=31993S3632