Table 1 gives an overview of the eight different pipelines linking NNS gas fields to the NNS gas processing plants, together with the parties' respective equity ownership and the name of the operator. The Miller pipeline currently transports only minimal quantities of gas and will be expanded (see recital 59). In addition, there is one pipeline (SEAL) currently under construction that will link NNS gas fields with a SNS processing facility. Arco has a [...] % interest in this pipeline.
Overall, BPA has an equity ownership in three pipelines and Acro has an equity ownership in two pipelines. There is no overlap in the parties' ownership interests and in four of the nine pipelines, the parties have no interest.
Table 1: NNS pipelines