Recital 9, Commission interpretative communication on concessions under Community law

In forcesince 29 Apr 2000

If recovery of expenditure were guaranteed by the awarding authority without the risk involved in the management of the construction, there would be no element of risk and the contract should be regarded as a works contract rather than a concession contract. Moreover, if the concessionaire receives whether directly or indirectly during the course of the contract or even when the contract comes to an end, payment (by way of reimbursement, covering losses etc.) other than connected with exploitation, the contract could no longer be regarded as a concession. In this situation, the compatibility of any subsequent financing should be considered in the light of any relevant Community law.