Art. 8 Directive (EU) 1999/31

Conditions of the permit

In forcesince 11 Dec 2008cited 33×

Member States shall take measures in order that:

(a)

the competent authority does not issue a landfill permit unless it is satisfied that:

(i)

without prejudice to Article 3(4) and (5), the landfill project complies with all the relevant requirements of this Directive, including the Annexes;

(ii)

the management of the landfill site will be in the hands of a natural person who is technically competent to manage the site; professional and technical development and training of landfill operators and staff are provided;

(iii)

the landfill shall be operated in such a manner that the necessary measures are taken to prevent accidents and limit their consequences;

(iv)

adequate provisions, by way of a financial security or any other equivalent, on the basis of modalities to be decided by Member States, has been or will be made by the applicant prior to the commencement of disposal operations to ensure that the obligations (including after-care provisions) arising under the permit issued under the provisions of this Directive are discharged and that the closure procedures required by Article 13 are followed. This security or its equivalent shall be kept as long as required by maintenance and after-care operation of the site in accordance with Article 13(d). Member States may declare, at their own option, that this point does not apply to landfills for inert waste;

(b)

the landfill project is in line with the relevant waste management plan or plans referred to in Article 7 of Directive 75/442/EEC;

(c)

prior to the commencement of disposal operations, the competent authority shall inspect the site in order to ensure that it complies with the relevant conditions of the permit. This will not reduce in any way the responsibility of the operator under the conditions of the permit.

The 10 that are cited most themselves, of 33.

  • Arrêt de la Cour (huitième chambre) du 25 février 2016. Commission européenne contre Royaume d'Espagne.Decision

    Il ressort de la jurisprudence de la Cour que l’obligation de faire en sorte que seules les décharges satisfaisant aux exigences de la directive 1999/31 demeurent exploitées implique également la désaffectation des sites qui n’ont …

    25 Feb 2016 · 62014CJ0454

  • Arrêt de la Cour (dixième chambre) du 25 avril 2013. Commission européenne contre République slovaque.Decision

    Il convient de relever que la Commission demande à la Cour de constater le manquement, relatif à l’autorisation d’exploitation de la décharge de Žilina – Považský Chlmec, uniquement en raison de l’absence d’un plan …

    25 Apr 2013 · 62011CJ0331

  • Arrêt de la Cour (troisième chambre) du 16 juillet 2015. Commission européenne contre République de Slovénie.Decisionrelated

    Il s’ensuit que le grief tiré de la violation des articles 5, paragraphe 3, sous e), 6, lu en combinaison avec la décision 2003/33, 7 à 9, 11 et 12 de la directive 1999/31 ainsi que des annexes I à III de cette dernière doit être …

    16 Jul 2015 · 62014CJ0140

  • Judgment of the Court (Fourth Chamber) of 4 July 2018. European Commission v Slovak Republic.Decision

    Article 14(a) of Directive 1999/31 requires the operator of an existing landfill site to prepare and present to the competent authorities, for their approval, a conditioning plan for the site in question and Article 14(b) of the directive …

    4 Jul 2018 · 62016CJ0626

  • Judgment of the Court (Fifth Chamber) of 10 September 2009. Commission of the European Communities v Hellenic Republic.Decisionrelated

    10 Sep 2009 · 62008CJ0286

  • Arrêt de la Cour (troisième chambre) du 16 juillet 2015. Commission européenne contre République de Bulgarie.Decision

    En outre, faire en sorte que seules les décharges satisfaisant aux exigences de cette directive demeurent exploitées implique également la désaffectation des sites qui n’ont pas obtenu, conformément à l’article 8 de ladite …

    16 Jul 2015 · 62014CJ0145

  • Judgment of the Court (Fifth Chamber) of 7 September 2016. European Commission v Hellenic Republic.Decision

    Article 8 of that directive provides: ‘Member States shall take measures in order that: the competent authority does not issue a landfill permit unless it is satisfied that: without prejudice to Article 3(4) and (5), the landfill project …

    7 Sep 2016 · 62014CJ0584

  • Judgment of the Court (Second Chamber), 9 April 2014. Ville d’Ottignies-Louvain-la-Neuve and Others v Région wallonne.Decisioninterprets

    In those circumstances, it is also necessary to consider whether Article 8 of Directive 1999/31, applicable to the facts of the main proceedings, precludes a national legislative provision such as that referred to by the referring court.

    9 Apr 2014 · 62013CJ0225

  • Judgment of the Court (Sixth Chamber) of 14 December 2023. European Commission v Romania.Decision

    By the judgment in Commission v Romania, the Court held that, by having failed to comply, as regards the 68 landfill sites covered by the Commission’s action, with the obligation to adopt all necessary measures to close down as soon as …

    14 Dec 2023 · 62022CJ0109

  • Arrêt de la Cour (dixième chambre) du 11 décembre 2014. Commission européenne contre République hellénique.Decisionrelated

    Par sa requête, la Commission européenne demande à la Cour de constater que, en ce qui concerne le site de mise en décharge de Kiato (Grèce): – en ne prenant pas les mesures nécessaires pour que la gestion des déchets sur le site …

    11 Dec 2014 · 62013CJ0677