Recital 46, Decision_act (EU) 1999/271

In force

In the opinion of Strintzis, the YEN's actions defined all factors of competition except prices on the international part of the Greece-Italy routes. Consequently, residual competition was very limited or even unworkable. In fact, the agreement on prices was a government-led and supervised cartel and not a cartel of individuals operating with the intention of maximising the profit of the participants. On the contrary, prices on Greece-Italy routes were lower than those on other international routes within the Community. As regards the gravity of the infringement, Strintzis submits that the involvement of the Greek authorities created confusion among the parties as to the applicable legal framework, and the price levels would have been the same even without the alleged price arrangements.

Ventouris Group Enterprises