, Decision_act (EU) 1998/637

In force

The 1998-2002 phase of the definitive plan, notified by Spain by letter dated 31 March 1998, aims at stepping up the modernisation, rationalisation and restructuring measures which coal undertakings must implement to reduce their production costs in order to receive the operating aid provided for in Article 3 of Decision No 3632/93/ECSC. Undertakings which are unable to reduce their production costs or which, despite reducing them, would still be far from achieving economic viability will have to step up their activity-reduction plan, as provided for by Article 4 of Decision No 3632/93/ECSC.

For the undertakings receiving operating aid under Article 3, Spain has set a target of a minimum net reduction in production of 1,9 million tonnes between l January 1998 and 23 July 2002, which by the time that the plan is completed will take their maximum production level down to 12,7 million tonnes, compared with 14,6 million tonnes in 1997.

In order to confirm the trend towards a reduction in those undertakings' production costs at 1992 prices, Spain must notify the Commission of 1997 production by 30 September 1998 at the latest. If production cost trends over the period 1994 to 1997 show that certain undertakings or production units fail to meet the conditions laid down in Article 3(2) of Decision No 3632/93/ECSC, Spain will submit proposals to the Commission to subject them to a closure plan before 23 July 2002 or, where appropriate, to a progressive and continuous activity-reduction plan, as provided for by Article 4 of the same Decision.

Throughout the period from 1998 to 2002 Spain must monitor production cost trends at each of the coal undertakings and, should they prove unable to generate a downward trend, will propose the necessary corrective measures to the Commission.

In view of the difficult geological conditions in Spain's coalfields, certain undertakings or production units must be subject to a closure plan before 23 July 2002 or, where appropriate, a progressive and continuous activity-reduction plan in order to qualify for the aid for the reduction of activity (Article 4 of Decision No 3632/93/ECSC).

The company Endesa's underground production capacity of 0,315 million tonnes will be subject to a closure plan to be completed before 23 July 2002.

Given the exceptional social and regional conditions in the Asturias coalfields, Hunosa, Minas de Figaredo SA and Mina de la Camocha SA will be subject to a progressive and continuous activity-reduction plan.