The Parties shall endeavour to resolve any dispute referred to in Article 245 of this Agreement by entering into consultations in good faith with the aim of reaching a mutually agreed solution.
A Party shall seek consultations by means of a written request to the other Party, copied to the Association Committee in Trade configuration, as set out in Article 408(4) of this Agreement, giving reasons for the request, including by identifying the measure at issue and the provisions referred to in Article 245 of this Agreement that it considers applicable.
Consultations shall be held within 30 days of the date of receipt of the request and take place, unless the Parties agree otherwise, in the territory of the Party to which the request is made. The consultations shall be deemed concluded within 30 days of the date of receipt of the request, unless both Parties agree to continue consultations. Consultations, in particular all information disclosed and positions taken by the Parties during the consultations, shall be confidential, and without prejudice to the rights of either Party in any further proceedings.
Consultations on matters of urgency, including those regarding perishable goods or seasonal goods or services shall be held within 15 days of the date of receipt of the request by the requested Party, and shall be deemed concluded within those 15 days unless both Parties agree to continue consultations.
If the Party to which the request is made does not respond to the request for consultations within ten days of the date of its receipt, or if consultations are not held within the timeframes laid down in paragraph 3 or in paragraph 4 of this Article respectively, or if the Parties agree not to have consultations, or if consultations have been concluded and no mutually agreed solution has been reached, the Party that sought consultations may have recourse to Article 248 of this Agreement.
During the consultations each Party shall deliver sufficient factual information, so as to allow a complete examination of the manner in which the measure at issue could affect the operation and the application of this Agreement.
Where consultations concern the transport of energy goods through networks and one Party views the resolution of the dispute as urgent because of an interruption, in full or in part, of transport of natural gas, oil or electricity between the Parties the consultations shall be held within three days of the date of submission of the request, and shall be deemed concluded three days after the date of submission of the request unless both Parties agree to continue consultations.