The M5 Junction 10 Development Consent Order 2025
Typestatutory instrumentDate4 Jun 2025Articles158Versions held2Cited by17 documentsLast changed3 Nov 2025
- 11Street works
- 12Application of the 1991 Act
- 13Construction and maintenance of new, altered or diverted streets and other structures
- 14Classification of roads, etc.
- 15Temporary stopping up and restriction of use of streets
- 16Permanent stopping up and restriction of use of streets and private means of access
- 17Access to works
- 21Compulsory acquisition of land
- 22Compulsory acquisition of land – incorporation of the mineral code
- 23Time limit for exercise of authority to acquire land compulsorily
- 24Compulsory acquisition of rights and imposition of restrictive covenants
- 25Public rights of way
- 26Private rights over land
- 27Modification of Part 1 of the 1965 Act
- 28Application of the 1981 Act
- 29Acquisition of subsoil or airspace only
- 30Rights under or over streets
- 31Temporary use of land for carrying out the authorised development
- 32Temporary use of land for maintaining the authorised development
- 33Statutory undertakers
- 34Apparatus and rights of statutory undertakers in stopped up streets
- 35Recovery of costs of new connections
- 1Interpretation
- 2Time limits
- 3Environmental Management Plan
- 4Details of consultation
- 5Landscaping
- 6Implementation and maintenance of landscaping
- 7Fencing
- 8Land and groundwater contamination
- 9Archaeology
- 10Protected species
- 11Detailed design
- 12Surface water drainage
- 13Flood compensation and flood storage
- 14Flood risk assessment
- 15Noise Mitigation
- 16Highway lighting
- 17Building and construction materials – highways
- 18Building and construction materials – structures
- 19Approvals and amendments to approved details
2 PROCEDURE FOR DISCHARGE OF REQUIREMENTS
- Schedule 3 CLASSIFICATION OF ROADS, ETC.
- Schedule 4 PERMANENT STOPPING UP OF HIGHWAYS AND PRIVATE MEANS OF ACCESS AND PROVISION OF NEW HIGHWAYS AND PRI
- Schedule 5 LAND IN WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED
- Schedule 7 LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
- Schedule 8 TREES SUBJECT TO TREE PRESERVATION ORDERS
1 FOR THE PROTECTION OF ELECTRICITY, GAS, WATER, AND SEWERAGE UNDERTAKERS
2 FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
3 FOR THE PROTECTION OF NATIONAL HIGHWAYS LIMITED
- 18Application etc.
- 19Interpretation
- 20General
- 21
- 22
- 23Works outside the Order limits
- 24Prior approvals and security
- 25Construction of the specified works
- 26Payments
- 27Provisional Certificate
- 28Opening
- 29Final condition survey
- 30Defects Period
- 31Final Certificate
- 32Security
- 33Commuted sums
- 34Insurance
- 35Indemnity
- 36Maintenance of the specified works
- 37Land
- 38Expert Determination
4 FOR THE PROTECTION OF SEVERN TRENT WATER LIMITED
5 FOR THE PROTECTION OF NATIONAL GRID ELECTRICITY DISTRIBUTION (WEST MIDLANDS) PLC
6 FOR THE PROTECTION OF WALES & WEST UTILITIES