The Associated British Ports (Immingham Eastern Ro-Ro Terminal) Development Consent Order 2024
The Associated British Ports (Immingham Eastern Ro-Ro Terminal) Development Consent Orde…
- 10Compulsory acquisition of rights
- 11Time limit for exercise of powers of compulsory acquisition
- 12Private rights over land
- 13Power to override easements and other rights
- 14Modification of Part 1 of the 1965 Act
- 15Application of the 1981 Act
- 16Statutory undertakers and operator of the electronic communications code network
- 17Recovery of costs of new connection
- 18Disregard of certain interests and improvements
- 19Set-off for enhancement in value of retained land
- 20No double recovery
chapter MISCELLANOUS AND GENERAL
- 29Defence to proceedings in respect of statutory nuisance
- 30Deemed marine licence
- 31Trees subject to a tree preservation order
- 32Application of landlord and tenant law
- 33Certification of plans and documents etc.
- 34Service of notices
- 35Arbitration
- 36Saving for Trinity House
- 37Provision against danger to navigation
- 38Lights on tidal works during construction
- 39Permanent light on tidal works
- 40Crown rights
- 41Protective provisions
- 42Byelaws relating to the authorised development
- 1Interpretation
- 2Time limit for commencement of the authorised development
- 3Amendments to approved details
- 4Construction hours – onshore works
- 5Travel plan
- 6Piling and marine construction works restrictions
- 7External appearance and height of the authorised development
- 8Onshore construction environmental management plan
- 9Surface water drainage
- 10Noise insulation
- 11Woodland management
- 12East Gate Improvements (Work No. 12)
- 13Operational freight management plan
- 14Lighting plan
- 15Flood risk assessment
- 16Contaminated land
- 17Materials Management Plan
- 18Impact Protection Measures for the IOT trunkway
- 19Impact Protection Measures for the IOT finger pier
- 20Amending the Port of Immingham Marine Operations Manual
2 PROCEDURE FOR DISCHARGE OF REQUIREMENTS
1 FOR THE PROTECTION OF THE STATUTORY CONSERVANCY AND NAVIGATION AUTHORITY FOR THE HUMBER
- 1Interpretation
- 2General
- 3Tidal Works: approval of detailed design
- 4Commencement of Tidal Works
- 5Discharges, etc.
- 6Obstruction in river
- 7Removal etc. of the Statutory Conservancy and Navigation Authority ’s moorings and buoys
- 8Navigational lights, buoys, etc.
- 9Removal of temporary works
- 10Protective action
- 11Abandoned or decayed works
- 12Facilities for navigation
- 13Sedimentation, etc.: remedial action
- 14Indemnity
- 15Statutory functions
- 16Operating procedures
- 17Oil Spillage Plan
2 FOR THE PROTECTION OF THE ENVIRONMENT AGENCY
3 FOR THE PROTECTION OF EXOLUM
4 FOR THE PROTECTION OF THE IOT OPERATORS
5 FOR THE PROTECTION OF NORTHERN POWERGRID
6 FOR THE PROTECTION OF ANGLIAN WATER
7 FOR THE PROTECTION OF NETWORK RAIL
8 FOR THE PROTECTION OF NORTH EAST LINCOLNSHIRE COUNCIL (AS LEAD LOCAL FLOOD AUTHORITY)
9 FOR THE PROTECTION OF CADENT GAS LIMITED AS GAS COMPANY
- 99Application
- 100Interpretation
- 101Protective works to buildings
- 102Acquisition of land
- 103Removal of apparatus
- 104Facilities and rights for alternative apparatus
- 105Retained apparatus: protection of Cadent
- 106Expenses
- 107Indemnity
- 108Enactments and agreements
- 109Co-operation
- 110
- 111Access
- 112Arbitration
- 113Notices
10 FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
11 FOR THE PROTECTION OF DFDS SEAWAYS PLC
12 FOR THE PROTECTION OF CLDN PORTS KILLINGHOLME LIMITED