The Great Yarmouth Third River Crossing Development Consent Order 2020
Typestatutory instrumentDate24 Sep 2020Articles211Versions held3Cited by18 documentsLast changed10 Jun 2021
- 9Power to alter layout, etc., of streets
- 10Street works
- 11Application of the 1991 Act
- 12Construction and maintenance of new, altered or diverted streets and other structures
- 13Classification of roads
- 14Permanent stopping up of streets and private means of access
- 15Temporary stopping up and restriction of use of streets
- 16Access to works
- 17Agreements with street authorities
- 18Traffic regulation measures
- 19Disapplication of obligations where undertaker is the street authority
- 25Compulsory acquisition of land
- 26Compulsory acquisition of land – incorporation of the mineral code
- 27Time limit for exercise of powers to possess land temporarily or to acquire land compulsorily
- 28Compulsory acquisition of rights
- 29Private rights over land
- 30Power to override easements and other rights
- 31Modification of Part 1 of the 1965 Act
- 32Application of the 1981 Act
- 33Acquisition of subsoil or airspace etc., only
- 34Rights over or under streets
- 43Operation of new bridge
- 44Extinguishment of right of navigation within the river Yare in connection with authorised development
- 45Closing the highway comprised in the new bridge and new bridge approaches
- 46Removal of vehicles
- 47Removal of falling loads and objects
- 48No apparatus in the new bridge or new bridge approaches without consent
- 49Subsidiary works and operations in the river Yare
- 50Protection against dredging
- 51Byelaws
- 52Fixed penalty notices
- 53Felling or lopping of trees
- 54Trees subject to tree preservation order or within conservation area
- 55Removal of human remains
- 56Deemed marine licence
- 57Application of landlord and tenant law
- 58Operational land for purposes of the 1990 Act
- 59Planning permission
- 60Undertaker's highway, road traffic and planning functions
- 61Defence to proceedings in respect of statutory nuisance
- 62Protective provisions
- 63Saving for Trinity House
- 64Certification of plans, etc.
- 65Service of notices
- 66Consents, agreements and approvals
- 67Arbitration
- 1Interpretation
- 2Time limits
- 3Commencement of the authorised development
- 4Design of the authorised development
- 5Detailed design of specified structures
- 6Code of construction practice
- 7Landscaping and ecological management plan
- 8Existing trees and hedgerows
- 9Contamination
- 10Emergency Preparedness and Response Plan
- 11Surface water drainage
- 12Lighting
- 13Completion and availability of particular works
- 14Archaeology
- 15Preliminary navigation risk assessment
- 16Signs at vessel waiting facilities
- 17Amendments to approved details
- 18Details of consultation
2 PROCEDURE FOR DISCHARGE OF REQUIREMENTS
- Schedule 3 STREETS SUBJECT TO PERMANENT LAYOUT AND OTHER ALTERATIONS
- Schedule 4 PERMANENT STOPPING UP OF STREETS AND PRIVATE MEANS OF ACCESS
- Schedule 5 TRAFFIC REGULATION MEASURES
- Schedule 6 LAND IN WHICH ONLY NEW RIGHTS MAY BE ACQUIRED
- Schedule 8 LAND IN WHICH ONLY AIRSPACE AND NEW RIGHTS MAY BE ACQUIRED
- Schedule 9 LAND OF WHICH ONLY TEMPORARY POSSESSION MAY BE TAKEN
- 4Notification of commencement and completion of licensed activities
- 5Construction method statement
- 6Noise registry
- 7Cofferdam dewatering and excavation method statement
- 8Vessels
- 9Marine pollution contingency plan
- 10Piling techniques
- 11Concrete and cement
- 12Coatings and treatments
- 13Spills, etc.
- 14Dropped objects
- 15Post construction
3 PROCEDURE FOR THE DISCHARGE OF CONDITIONS
1 FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
2 FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
3 FOR THE PROTECTION OF ANGLIAN WATER
4 FOR THE PROTECTION OF THE ENVIRONMENT AGENCY
5 FOR THE PROTECTION OF THE WAVENEY, LOWER YARE AND LOTHINGLAND INTERNAL DRAINAGE BOARD
Source: legislation.gov.uk (The National Archives), UK legislation with its point-in-time versions. Official publication. Reuse: Open Government Licence v3.0.