, The East Anglia THREE Offshore Wind Farm (Amendment) Order 2019

In force

2019 No. 997

Infrastructure Planning

The East Anglia THREE Offshore Wind Farm (Amendment) Order 2019

Made

6th June 2019

Coming into force

7th June 2019

An application has been made, under paragraph 2 of Schedule 6 to the Planning Act 2008, to the Secretary of State in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for a non-material change to The East Anglia THREE Offshore Wind Farm Order 2017 (“the 2017 Order”).

The Secretary of State, having considered the application, the responses to the publicity and consultation required by regulations 6 and 7 of the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011, has decided to make this Order amending the 2017 Order.

Accordingly, the Secretary of State, in exercise of the powers in paragraph 2 of Schedule 6 to the Planning Act 2008, makes the following Order: