The Construction (Design and Management) Regulations 2015
Typestatutory instrumentDate22 Jan 2015Articles77Versions held4Cited by37 documentsLast changed1 Jan 2018
- 8General duties
- 9Duties of designers
- 10Designs prepared or modified outside Great Britain
- 11Duties of a principal designer in relation to health and safety at the pre-construction phase
- 12Construction phase plan and health and safety file
- 13Duties of a principal contractor in relation to health and safety at the construction phase
- 14Principal contractor's duties to consult and engage with workers
- 15Duties of contractors
- 16Application of Part 4
- 17Safe places of construction work
- 18Good order and site security
- 19Stability of structures
- 20Demolition or dismantling
- 21Explosives
- 22Excavations
- 23Cofferdams and caissons
- 24Reports of inspections
- 25Energy distribution installations
- 26Prevention of drowning
- 27Traffic routes
- 28Vehicles
- 29Prevention of risk from fire, flooding or asphyxiation
- 30Emergency procedures
- 31Emergency routes and exits
- 32Fire detection and fire-fighting
- 33Fresh air
- 34Temperature and weather protection
- 35Lighting
Source: legislation.gov.uk (The National Archives), UK legislation with its point-in-time versions. Official publication. Reuse: Open Government Licence v3.0.