The Offshore Installations (Offshore Safety Directive) (Safety Case etc.) Regulations 2015
Typestatutory instrumentDate19 Mar 2015Articles242Versions held6Cited by53 documentsLast changed6 Apr 2026
- Preamble
- 1Citation and commencement
- 2Interpretation
- 3Communication and storage of information by electronic means
- 4Application and extent
- 5Duties of licensee
- 6Capacity of operator to meet requirements
- 7Corporate major accident prevention policy
- 8Safety and environmental management system
- 9Establishment of verification scheme
- 10Other provisions as to verification schemes
- 11Establishment of well examination scheme
- 12Other provisions as to well examination schemes
- 13Description of verification scheme and well examination scheme
- 14Defence
- 15Design and relocation notifications for production installation
- 16Management and control of major accident hazards
- 17Safety case for production installation
- 18Safety case for non-production installation
- 19Design notification and safety case for non-production installation to be converted
- 20Safety case for dismantling fixed installation
- 21Notification of well operations
- 22Notification of combined operations
- 23Review of safety case
- 24Revision of safety case
- 25Power of competent authority in relation to safety cases and related documents
- 26Power of the competent authority to prohibit operations
- 27Keeping of documents
- 28Duty to conform with safety case and notifications of operation
- 29Duty to control risk
- 30Internal emergency response
- 31Communication of national arrangements for confidential reporting of safety concerns etc.
- 32Standards and guidance on best practice
- 33Notification of major accident etc.
- 34Information on operations conducted outside of the European Union , Great Britain and external waters
- 35Exemptions
- 36Enforcement
- 37Appeals
- 38Amendments and revocations
- 39Transitional provisions and savings
- 40Penalties
- 41Review
- 2General saving of the 2005 regime
- 3Continued application of the 2005 regime to existing and proposed non-production installations
- 4Continued application of the 2005 regime to existing and proposed production installations
- 5Continued application of the 2005 regime to well operations
- 6Design notification for production installations to be established during transitional period
- 7Design notification: election to prepare notification under these Regulations
- 8Election to prepare a safety case under these Regulations
- 9Treatment of current safety cases for installations continuing under the 2005 regime
- 10
- 11
3 Transition from the 2005 regime
Source: legislation.gov.uk (The National Archives), UK legislation with its point-in-time versions. Official publication. Reuse: Open Government Licence v3.0.