, The Renewables Obligation Order 2015

In forcesince 1 Dec 2015

Way of generating electricity | Amount of electricity (in megawatt hours) to be stated in a ROC issued in respect of the qualifying proportion of electricity generated using 2015/16 capacity | Amount of electricity (in megawatt hours) to be stated in a ROC issued in respect of the remainder of the electricity generated using 2015/16 capacity

Co-firing of regular bioliquid with CHP | 1 | 2

Dedicated biomass with CHP |

10 19

2 3

High-range co-firing with CHP |

5 7

10 9

Low-range co-firing with CHP | 1 | 2

Mid-range co-firing with CHP |

10 11

5 3

Station conversion with CHP |

2 3

1

Unit conversion with CHP |

2 3

1