The Walney Extension Offshore Wind Farm Order 2014
Typestatutory instrumentDate7 Nov 2014Articles168Versions held6Cited by14 documentsLast changed28 Dec 2017
- Preamble
- 1Citation and commencement
- 2Interpretation
- 3Development consent etc. granted by the Order
- 4Maintenance of authorised project
- 5Benefit of the Order
- 6Operation of generating station
- 7Application of the Hedgerows Regulations 1997
- 8Defence to proceedings in respect of statutory nuisance
- 9Requirements, appeals etc.
- 10Street works
- 11Temporary stopping up of streets
- 12Temporary stopping up of public rights of way
- 13Access to works
- 14Agreements with street authorities
- 15Discharge of water
- 16Protective work to buildings
- 17Authority to survey and investigate the land
- 18Removal of human remains
- 19Compulsory acquisition of land
- 20Time limit for exercise of authority to acquire land compulsorily
- 21Compulsory acquisition of rights
- 22Private rights
- 23Application of the Compulsory Purchase (Vesting Declarations) Act 1981
- 24Acquisition of subsoil only
- 25Acquisition of part of certain properties
- 26Rights under or over streets
- 27Temporary use of land for carrying out the authorised project
- 28Temporary use of land for maintaining the authorised project
- 29Statutory undertakers
- 30Recovery of costs of new connections
- 31Application of landlord and tenant law
- 32Operational land for the purposes of the 1990 Act
- 33Felling or lopping of trees and the removal of hedgerows
- 34Trees subject to tree preservation orders
- 35Public rights of navigation
- 36Abatement of works abandoned or decayed
- 37Deemed licences under the Marine and Coastal Access Act 2009
- 38Saving for Trinity House
- 39Crown rights
- 40Certification of plans etc.
- 41Protective provisions
- 42Arbitration
- 1Time limits
- 2Detailed offshore design parameters
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12Air traffic services at Warton Aerodrome
- 13Primary surveillance radars at St Annes and Lowther Hill
- 14Offshore decommissioning
- 15Stages of authorised development onshore
- 16Detailed design approval onshore
- 17
- 18Provision of landscaping
- 19Implementation and maintenance of landscaping
- 20Highway accesses
- 21Public Access Strategy
- 22Public rights of way
- 23Fencing and other means of enclosure
- 24Surface and foul water drainage
- 25Contaminated land and contaminated groundwater
- 26Archaeology onshore
- 27Code of Construction Practice (CoCP)
- 28Construction and environmental management plan
- 29Emergency response plan
- 30European protected species
- 31Construction Traffic Management Plan
- 32Port Construction Traffic Management Plan (Port CTMP)
- 33Construction hours
- 34Control of noise during construction
- 35Control of noise during operational phase
- 36Control of air quality
- 37Control of artificial light emissions
- 38Flood risk
- 39Restoration of land used temporarily for construction
- 40Onshore decommissioning
- 41Requirement for written approval
- 42Amendments to approved details
- Schedule 2 STREETS SUBJECT TO STREET WORKS
- Schedule 3 STREETS TO BE TEMPORARILY STOPPED UP
- Schedule 4 PUBLIC RIGHTS OF WAY TO BE TEMPORARILY STOPPED UP
- Schedule 5 ACCESS TO WORKS
- Schedule 6 LAND IN WHICH ONLY NEW RIGHTS ETC., MAY BE ACQUIRED
- 1Design parameters for wind turbines
- 2Design Parameters for WTG foundations
- 3Design parameters for inter-array cables
- 4Design parameters for other deposits
- 5Notifications and inspections
- 6Reporting of engaged agents, contractors and vessels
- 7Equipment and operation of vessels engaged in licensed activities
- 8Chemicals, drilling and debris
- 9Force majeure
- 10Seasonal restrictions in respect of fish spawning
- 11Pre-construction plans and documentation
- 12Pre-construction surveying and monitoring
- 13Construction monitoring
- 14Post construction monitoring
- 15Offshore Decommissioning
- 16Offshore Safety Management
- 17Aids to navigation
- 18Provision against danger to navigation
- 19Requirement for written approval
- 20Amendments to approved details
- 1Design parameters for offshore substation platforms and export cable systems
- 2Design parameters for other deposits
- 3Notifications and inspections
- 4Reporting of engaged agents, contractors and vessels
- 5Equipment and operation of vessels engaged in licensed activities
- 6Chemicals, drilling and debris
- 7Force majeure
- 8Restrictions on works in the Inter-tidal Area
- 9Seasonal restrictions in respect of fish spawning
- 10Pre-construction plans and documentation
- 11Pre-construction surveying and monitoring
- 12Construction monitoring
- 13Post construction monitoring
- 14Offshore Decommissioning
- 15Offshore Safety Management
- 16Aids to navigation
- 17Provision against danger to navigation
- 18Requirement for written approval
- 19Amendments to approved details