The Network Rail (North Doncaster Chord) Order 2012
Typestatutory instrumentDate16 Oct 2012Articles92Versions held4Cited by15 documentsLast changed28 Dec 2017
- 10Power to alter layout, etc., of streets
- 11Street works
- 12Construction and maintenance of new or altered streets
- 13Stopping up of streets
- 14Application of the 1991 Act
- 15Temporary stopping up of streets
- 16Access to works
- 17Agreements with street authorities
- 18Construction of bridges and tunnels
- 19Level crossings
- 22Compulsory acquisition of land
- 23Time limit for exercise of authority to acquire land compulsorily
- 24Compulsory acquisition of rights
- 25Private rights
- 26Application of Compulsory Purchase (Vesting Declarations) Act 1981
- 27Acquisition of subsoil or airspace only
- 28Acquisition of part of certain properties
- 29Rights under or over streets
- 30Temporary use of land for carrying out the authorised development
- 31Temporary use of land for maintaining authorised development
- 32Statutory undertakers
- 33Apparatus and rights of statutory undertakers in stopped up streets
- 34Recovery of costs of new connections
- 1Interpretation
- 2Stages of authorised development
- 3In accordance with approved details
- 4Landscaping
- 5Implementation and maintenance of landscaping
- 6Highway accesses
- 7Archaeology
- 8Contract Requirements – Environment
- 9Ecological Management Plan
- 10Alteration, reconstruction or replacement of buildings
- 11Alteration, reconstruction or replacement of level crossings
- 12Amendments to approved details
- 13Flood Risk Assessment and Piling Method Statement
Source: legislation.gov.uk (The National Archives), UK legislation with its point-in-time versions. Official publication. Reuse: Open Government Licence v3.0.