, EA 2008

In forcesince 20 May 2009

SCHEDULE 2A

property schemes

SECTION 6E

Scheme-making power

1 (1) This paragraph applies where—

(a)

a tender exercise is held in relation to an offshore transmission licence,

(b)

any transmission assets have been transferred to the successful bidder or, for operational purposes, it is necessary for any transmission assets to be so transferred, and

(c)

those assets were not constructed or installed by the successful bidder.

(2)

The Authority may, on an application under paragraph 3, make a scheme (“a property scheme”) providing for—

(a)

the transfer to the successful bidder of, or

(b)

the creation in favour of the successful bidder of rights in relation to,

property, rights or liabilities.

(3)

In sub-paragraph (1)—

(a)

“transmission assets” means the transmission system in respect of which the offshore transmission licence is (or is to be) granted or anything which forms part of that system, and

(b)

the reference to the successful bidder in paragraph (c) includes, if the successful bidder is a body corporate, a reference to any body corporate which was associated with the successful bidder at the time the transmission assets were constructed or installed.

(4)

Until such time as section 180 of the Energy Act 2004 (meaning of “high voltage line”) comes into force, “transmission system” in sub-paragraph (3)(a) includes a system which, if that section were in force, would be a transmission system.

Further provision about the content of a scheme

2 (1) A property scheme may also contain—

(a)

provision for the creation, in relation to property which the scheme transfers, of an interest in or right over the property in favour of the asset owner;

(b)

provision for the creation of any rights or liabilities as between the asset owner and the successful bidder;

(c)

provision for imposing on the asset owner or the successful bidder an obligation to enter into a written agreement with, or to execute an instrument of another kind in favour of, the other;

(d)

provision requiring the successful bidder to pay the asset owner compensation;

(e)

provision requiring the asset owner to pay the successful bidder compensation;

(f)

supplemental, incidental and consequential provision.

(2)

The property, rights and liabilities which may be transferred by a property scheme include property, rights or liabilities which would not otherwise be capable of being transferred.

(3)

If a property scheme provides for the division of an estate or interest in land and any rent is—

(a)

payable in respect of the estate or interest under a lease, or

(b)

charged on the estate or interest,

the scheme may contain provision for apportionment or division so that one part is payable in respect of, or charged on, only one part of the estate or interest and the other part is payable in respect of, or charged on, only the other part of the estate or interest.

(4)

A property scheme which contains provision which affects a third party may also contain provision requiring the successful bidder or the asset owner to pay the third party compensation.

Applications for schemes

3 (1) An application for a property scheme may be made by—

(a)

the preferred bidder,

(b)

the successful bidder, or

(c)

a person who owns the property, rights and liabilities in relation to which provision of a kind mentioned in paragraph 1(2) is proposed to be included in the scheme.

(2)

An application must specify—

(a)

the property, rights and liabilities in relation to which provision of a kind mentioned in paragraph 1(2) is proposed to be included in the scheme,

(b)

the name and address of the non-applicant party, and

(c)

the name and address of each third party whom the applicant considers would be affected by a provision of the proposed property scheme.

(3)

All property, rights and liabilities specified in an application in accordance with sub-paragraph (2)(a) must belong to the same person.

(4)

A person may make more than one application under this paragraph.

Timing of applications

4 An application for a property scheme, in relation to a tender exercise, may only be made at a time when—

(a)

a notice identifying the preferred bidder has been published under paragraph 35(2) (and not withdrawn), or

(b)

a notice has been published under paragraph 36 identifying the successful bidder.

5 (1) No application may be made for a property scheme after the end of the transitional period.

(2)

Subject to sub-paragraph (3), “the transitional period” means the period of 4 years beginning with the day on which section 92 of the Energy Act 2004 (competitive tenders for offshore transmission licences) comes into force.

(3)

Before the end of the transitional period, the Secretary of State may, by order, extend that period by a period specified in the order.

(4)

An order under sub-paragraph (3) may relate to a particular case, or to cases of a particular description, only.

(5)

The total transitional period in any case must not exceed 7 years.

(6)

Before making an order under sub-paragraph (3), the Secretary of State must give notice of the proposal to extend the transitional period.

(7)

The notice must—

(a)

state that the Secretary of State proposes to make an order extending the transitional period and set out the terms of the proposed order,

(b)

state the reasons why the Secretary of State proposes to make the order, and

(c)

specify the time (not being less than 28 days from the date of publication of the notice under sub-paragraph (8)(b)) within which representations with respect to the proposals may be made.

(8)

The notice must be given—

(a)

by serving a copy of it on the Authority, and

(b)

by publishing it in such manner as the Secretary of State considers appropriate for bringing it to the attention of—

(i)

the owner of any property, right or liability who may have an interest in the making of the proposed order, and

(ii)

if the order relates to a case where a tender exercise has begun, any person who has submitted an application for the offshore transmission licence to which the exercise relates.

Notifying the non-applicant party

6 (1) On receipt of an application for a property scheme, the Authority must serve on the non-applicant party a notice which—

(a)

invites the non-applicant party to make representations to the Authority about the application within the period specified in the notice (being not less than 21 days) beginning with the day on which the notice is served, and

(b)

describes the effect of paragraphs 9 and 11.

(2)

A notice under sub-paragraph (1) must be accompanied by—

(a)

a copy of the application, and

(b)

a notice under paragraph 16 which complies with the requirements of sub-paragraph (3).

(3)

The notice under paragraph 16 must require the non-applicant party to provide the Authority, within the period specified in the notice (being not less than 7 days) beginning with the day on which the notice is served, with—

(a)

the name and address of each person to whom sub-paragraph (4) applies, or

(b)

if the non-applicant party does not consider that there is any person to whom that sub-paragraph applies, a statement to that effect.

(4)

This sub-paragraph applies to a person—

(a)

whom the non-applicant party considers is a third party who would be affected by a provision of the proposed property scheme, and

(b)

whose name and address were not specified in the application under paragraph 3(2)(c).

Notifying third parties

7 (1) As soon as reasonably practicable after receiving the information required by a notice within paragraph 6(2)(b), the Authority must serve on each person within sub-paragraph (2)—

(a)

a copy of the application, and

(b)

a notice inviting that person to make representations to the Authority about the application within the period specified in the notice (being not less than 21 days) beginning with the day on which the notice is served.

(2)

A person is within this sub-paragraph if the person's name and address were—

(a)

specified in the application in accordance with paragraph 3(2)(c), or

(b)

provided to the Authority in response to a notice within paragraph 6(2)(b).

Publishing the application

8 As soon as reasonably practicable after an application is made for a property scheme, the Authority must publish a notice which—

(a)

states that an application for a property scheme has been made,

(b)

states the names of the applicant and the non-applicant party, and

(c)

contains a general description of the property scheme to which the application relates.

Supplementing the application

9 (1) The non-applicant party may, by notice served on the Authority during the period mentioned in paragraph 6(1)(a), modify the application so as to specify additional property, rights or liabilities of the asset owner in relation to which provision of a kind mentioned in paragraph 1(2) is proposed to be included in the scheme.

(2)

Where an application is modified by a notice under sub-paragraph (1) (a “modification notice”), this Schedule has effect from that time as if any additional property, rights or liabilities specified in the notice had been specified in the application in accordance with paragraph 3(2)(a).

(3)

A modification notice must specify the name and address of each person—

(a)

whom the non-applicant party considers to be a third party who would be affected by a provision of the proposed property scheme as modified by the notice, and

(b)

who is not within paragraph 7(2).

(4)

On receipt of a modification notice, the Authority must serve on the applicant a notice (a “warning notice”) which invites the applicant to make representations to the Authority about the modification notice within the period specified in the warning notice (being a period of not less than 21 days) beginning with the day on which the warning notice is served.

(5)

A warning notice must be accompanied by—

(a)

a copy of the modification notice,

(b)

a notice under paragraph 16 which complies with the requirements of sub-paragraph (6), and

(c)

a copy of any information provided by the non-applicant to the Authority in response to a notice within paragraph 6(2)(b).

(6)

The notice under paragraph 16 must require the applicant to provide the Authority, within the period specified in the notice (being not less than 7 days) beginning with the day on which the notice is served, with—

(a)

the name and address of each person to whom sub-paragraph (7) applies, or

(b)

if the applicant does not consider that there is any person to whom that sub-paragraph applies, a statement to that effect.

(7)

This sub-paragraph applies to a person—

(a)

whom the applicant considers is a third party who would be affected by a provision of the proposed property scheme as modified by the modification notice, and

(b)

whose name and address were not—

(i)

specified in the application in accordance with paragraph 3(2)(c),

(ii)

provided to the Authority in response to a notice within paragraph 6(2)(b), or

(iii)

specified in the modification notice under sub-paragraph (3).

(8)

As soon as reasonably practicable after receiving the information required by a notice within sub-paragraph (5)(b), the Authority must serve on each person within sub-paragraph (9) a notice inviting that person to make representations to the Authority about the modification notice within the period specified in the notice (being a period of not less than 21 days) beginning with the day on which the notice is served.

(9)

A person is within this sub-paragraph if the person's name and address were—

(a)

specified in the application in accordance with paragraph 3(2)(c),

(b)

provided to the Authority in response to a notice within paragraph 6(2)(b) or sub-paragraph (5)(b) of this paragraph, or

(c)

specified in the modification notice.

(10)

A notice under sub-paragraph (8) must be accompanied by—

(a)

a copy of the modification notice, and

(b)

if a copy of the application has not previously been served on the person under paragraph 7(1), a copy of the application.

10 As soon as reasonably practicable after the Authority receives a modification notice, the Authority must publish a notice which—

(a)

states that a modification notice has been served on the Authority in relation to an application,

(b)

states the names of the applicant and the non-applicant party in relation to the application, and

(c)

contains a general description of the modifications made to the application by the modification notice.

Restricting or withdrawing the application

11 (1) Where an application for a property scheme has been made, the applicant and the non-applicant party may, by a notice served by them jointly on the Authority—

(a)

restrict the property, rights and liabilities in relation to which provision of a kind mentioned in paragraph 1(2) is proposed, or

(b)

withdraw the application.

(2)

Where a notice is served under sub-paragraph (1) the Authority must serve a copy of the notice on any person served with a notice in relation to the application under paragraph 7(1) or 9(8).

(3)

A notice may be served under sub-paragraph (1) at any time before a property scheme is made in response to the application.

(4)

If, at any time, a notice specifying the preferred bidder, in relation to a tender exercise, is withdrawn under paragraph 35, any application for a property scheme previously made, in relation to that exercise, by the preferred bidder or by the asset owner (unless previously withdrawn under sub-paragraph (1)) is treated as withdrawn at that time.

(5)

Where an application is withdrawn by virtue of sub-paragraph (4), the Authority must serve notice to that effect on—

(a)

the asset owner, and

(b)

any person served with a notice in relation to the application under paragraph 7(1) or 9(8).

(6)

If a notice is served under sub-paragraph (1) or an application is withdrawn by virtue of sub-paragraph (4), the Authority may direct the applicant or the non-applicant party (or both) to make a payment to a person within sub-paragraph (7) in respect of the costs incurred by such a person in connection with the application.

(7)

Those persons are—

(a)

the Authority;

(b)

any third party affected by a provision of the proposed property scheme.

(8)

A determination under sub-paragraph (6) must be made on the basis of what is just in all the circumstances of the case.

(9)

The Authority must serve notice of a direction given under sub-paragraph (6) on—

(a)

the applicant (if not the recipient of the direction),

(b)

the non-applicant party (if not the recipient of the direction), and

(c)

any person served with a notice in relation to the application under paragraph 7(1) or 9(8).

(10)

Any sums received by the Authority under sub-paragraph (6) are to be paid into the Consolidated Fund.

The Authority's functions in relation to applications

12 (1) On an application for the making of a property scheme, the Authority must determine whether the proposed provision in relation to any property, right or liability specified in the application in accordance with paragraph 3(2)(a) is necessary or expedient for operational purposes.

(2)

Sub-paragraph (1) does not apply, in relation to any property, right or liability specified in the application, if the successful bidder and the asset owner agree that the proposed provision, in relation to that property, right or liability, is necessary or expedient for operational purposes.

(3)

If the Authority determines under sub-paragraph (1) that the proposed provision, in relation to any property, right or liability specified in the application, is not necessary or expedient for operational purposes—

(a)

it must refuse the application in relation to the property, right or liability, but

(b)

it may serve on the applicant and the non-applicant party a notice proposing, in relation to the property, right or liability, alternative provision of a kind mentioned in paragraph 1(2).

(4)

A notice under sub-paragraph (3)(b) must—

(a)

invite the recipient to make representations to the Authority about the proposed alternative provision within the period specified in the notice (being not less than 21 days) beginning with the day on which the notice is served, and

(b)

be accompanied by a notice under paragraph 16 which complies with the requirements of sub-paragraph (5).

(5)

The notice under paragraph 16 must require the recipient of the notice to provide the Authority, within the period specified in the notice (being not less than 7 days) beginning with the day on which the notice is served, with—

(a)

the name and address of each person to whom sub-paragraph (6) applies, or

(b)

if the recipient does not consider that there is any such person, a statement to that effect.

(6)

This sub-paragraph applies to a person—

(a)

whom the recipient of the notice considers is a third party who would be affected by the Authority's proposed alternative provision, and

(b)

whose name and address were not—

(i)

specified in the application in accordance with paragraph 3(2)(c) or in a modification notice under paragraph 9(3), or

(ii)

provided to the Authority in response to a notice within paragraph 6(2)(b) or 9(5)(b).

(7)

As soon as reasonably practicable after receiving the information required by a notice within sub-paragraph (4)(b), the Authority must serve on each person within sub-paragraph (8)—

(a)

if a copy of the application has not previously been served on the person under paragraph 7(1) or 9(8), a copy of the application,

(b)

if a copy of any modification notice has not previously been served on the person under paragraph 9(8), a copy of the notice,

(c)

a copy of the notice served under sub-paragraph (3)(b), and

(d)

a notice inviting that person to make representations to the Authority about the proposed alternative provision within the period specified in the notice beginning with the day on which the notice is served.

(8)

A person is within this sub-paragraph if the person's name and address were—

(a)

specified in the application in accordance with paragraph 3(2)(c) or in a modification notice under paragraph 9(3),

(b)

provided to the Authority in response to a notice within sub-paragraph (4)(b) or paragraph 6(2)(b) or 9(5)(b).

(9)

The period specified under sub-paragraph (7)(d) must be not less than—

(a)

in the case of a person whose name and address were provided to the Authority in response to a notice within sub-paragraph (4)(b), 21 days, and

(b)

in any other case, 14 days.

(10)

Having considered any representations made in accordance with sub-paragraph (4)(a) or (7)(d), the Authority must determine whether the proposed alternative provision is necessary or expedient for operational purposes.

(11)

If—

(a)

the Authority determines under sub-paragraph (1) that the proposed provision, in relation to any property, right or liability specified in the application, is necessary or expedient for operational purposes,

(b)

the successful bidder and the asset owner agree that that is the case, or

(c)

the Authority determines under sub-paragraph (10) that the proposed alternative provision, in relation to any property, right or liability, is necessary or expedient for operational purposes,

the Authority must, subject to paragraphs 13 and 14(4), make a property scheme in relation to that property, right or liability.

(12)

In this paragraph “the proposed provision”, in relation to any property, right or liability, means the provision of a kind mentioned in paragraph 1(2) which the application proposes is made in relation to that property, right or liability (having regard to any modification under paragraph 9 or restriction under paragraph 11).

13 (1) On an application for a property scheme, no scheme may be made until—

(a)

the offshore transmission licence has been issued to the successful bidder, and

(b)

the relevant co-ordination licence holder has given the Authority, in accordance with the co-ordination licence, a completion notice in relation to the transmission system to which the property scheme relates.

(2)

For this purpose—

(a)

a “completion notice”, in relation to a transmission system, is a notice which states that it would be possible to carry on an activity to which section 4(1)(b) applies by making available for use that system;

(b)

a property scheme relates to a transmission system if the property, rights and liabilities in respect of which the scheme makes provision of a kind mentioned in paragraph 1(2) are relevant to the performance by the successful bidder of its licensed functions in relation to that system.

(3)

Until such time as section 180 of the Energy Act 2004 (meaning of “high voltage line”) comes into force—

(a)

the references in sub-paragraphs (1) and (2) to a transmission system include a system which, if that section were in force, would be a transmission system (“an offshore 132 kilovolt system”), and

(b)

that section is to be treated as if it were in force for the purposes of determining under sub-paragraph (2)(a) whether it would be possible to carry on an activity to which section 4(1)(b) applies by making available for use an offshore 132 kilovolt system.

(4)

In this paragraph—

“licensed functions” means—

functions under the offshore transmission licence to which the tender exercise relates, and

functions which the successful bidder has, in the capacity of holder of that licence, under or by virtue of any enactment;

“relevant co-ordination licence holder” means—

the holder of a co-ordination licence to whom a person has applied (in accordance with any provision made by that licence) for an offer of connection to and use of a transmission system for the purposes of which the tender exercise is held, or

where the tender exercise is held for the purposes of a connection request within the meaning of section 6D(3)(b), the holder of a co-ordination licence to whom a connection request within the meaning of section 6D(3)(a) would have been made if section 180 of the Energy Act 2004 had been in force and, accordingly, the tender exercise had been held for the purposes of such a request.

Terms of a property scheme

14 (1) Where the Authority is required to make a property scheme, the terms of the scheme must be such as the successful bidder and the asset owner may agree or, if they fail to agree, as the Authority may determine.

This is subject to sub-paragraphs (2) to (9).

(2)

A property scheme must not provide for any provision to come into operation before the end of the period of 21 days beginning with the day on which the scheme is made.

(3)

In determining the terms of a scheme under sub-paragraph (1), the Authority must, in particular, determine whether the scheme should include provision for compensation to be paid—

(a)

by the successful bidder to the asset owner, or

(b)

by the asset owner to the successful bidder,

and, if so, what that provision should be.

(4)

The Authority may not include in a property scheme provision which would adversely affect a third party unless it determines that it is necessary or expedient for operational purposes for the provision to be made.

(5)

Where the Authority includes in a property scheme provision which would adversely affect a third party, the Authority must determine whether the scheme should include provision for compensation and, if so, what that provision should be.

This article is long: the rest is at the official publication.