, The Town and Country Planning (Fees for Applications and Deemed Applications) (Scotland)…
Changed on 1 Apr 2022
EXPLANATORY NOTE
(This note is not part of the Regulations)
These Regulations amend the Town and Country Planning (Fees for Applications and Deemed Applications) (Scotland) Regulations 2004 (“the principal Regulations”) to increase certain planning fees.
Regulation 2 inserts a new table of fees in Part III of the schedule of the principal Regulations. The fees which changed are shown in the table below.
Regulation 3 contains a saving provision.
A Business and Regulatory Impact Assessment has been prepared and placed in the Scottish Parliament Information Centre. It can be obtained free of charge from the Scottish Government Planning Directorate, Area 2H, Victoria Quay, Edinburgh, EH6 6QQ.
Category of development | Type of application | Old fee | New fee
1. Construction of buildings, structures or erections for use as residential accommodation (other than development within category 6). | Applications for planning permission in principle. | £401 for each 0.1 hectare, subject to a maximum of £10,028; or £401 if only one dwellinghouse. | Where the site area does not exceed 2.5 hectares, £401 for each 0.1 hectare or £401 if only one dwellinghouse.
Where the site area exceeds 2.5 hectares, £10,028 plus £100 for each 0.1 hectare in excess of 2.5 hectares, subject to an overall maximum of £62,500.
Applications other than for planning permission in principle. | £401 for each dwellinghouse, subject to a maximum of £20,055. | Where there are no more than 50 dwellinghouses, £401 for each.
Where there are more than 50 dwellinghouses, £20,050 plus £200 for each dwellinghouse in excess of 50, subject to an overall maximum of £124,850.
2. The erection of buildings (other than buildings within category 1, 3, 4 or 6). | Applications for planning permission in principle. | £401 for each 0.1 hectare, subject to a maximum of £10,028. | Where the site area does not exceed 2.5 hectares, £401 for each 0.1 hectare.
Where the site area exceeds 2.5 hectares, £10,028 plus £100 for each 0.1 hectare in excess of 2.5 hectares, subject to an overall maximum of £62,500.
Where the area of floor space does not exceed 40 square metres, £202. | No change.
Applications other than for planning permission in principle. | Where the area of floor space exceeds 40 square metres but not 75 square metres, £401. | No change.
Where the area of floor space exceeds 75 square metres, £401 for each 75 square metres, subject to a maximum of £20,055. | Where the area of floor space exceeds 75 square metres but not 3,750 square metres, £401 for each 75 square metres.
Where the floor space exceeds 3,750 square metres, £200 for each 75 square metres, subject to an overall maximum of £125,000.
5. The erection, alteration or replacement of plant or machinery. | Applications for planning permission. | £401 for each 0.1 hectare, subject to a maximum of £20,055. | Where the site area does not exceed 5 hectares, £401 for each 0.1 hectare.
Where the site area exceeds 5 hectares, £20,050 plus £200 for each 0.1 hectare in excess of 5 hectares, subject to an overall maximum of £125,000.
8. The carrying out of any operations connected with exploratory drilling for oil or natural gas. | Applications for planning permission. | £401 for each 0.1 hectare, subject to a maximum of £30,240. | Where the site area does not exceed 7.6 hectares, £401 for each 0.1 hectare.
Where the site area exceeds 7.6 hectares, £30,240 plus £200 for each 0.1 hectare in excess of 7.6 hectares, subject to an overall maximum of £125,000.
10. The carrying out of any operations not coming within any other category: the winning and working of minerals. | Applications for planning permission. | £202 for each 0.1 hectare, subject to a maximum of £30,240. | Where the site area does not exceed 15 hectares, £202 for each 0.1 hectare.
Where the site area exceeds 15 hectares, £30,240 plus £100 for each 0.1 hectare in excess of 15 hectares, subject to an overall maximum of £125,000.
11. The change of use of a building to use as one or more dwellinghouses. | Applications for planning permission. | £401 for each additional dwellinghouse to be created, subject to a maximum of £20,055. | Where no more than 50 additional dwellinghouses are created, £401 for each.
Where more than 50 additional dwellinghouses are created, £20,050 plus £200 for each dwellinghouse in excess of 50, subject to an overall maximum of £124,850.
12(a). The use of land for the disposal of refuse or waste materials, including mineral waste. | Applications for planning permission. | £202 for each 0.1 hectare, subject to a maximum of £30,240. | Where the site area does not exceed 15 hectares, £202 for each 0.1 hectare.
Where the site area exceeds 15 hectares, £30,240 plus £100 for each 0.1 hectare in excess of 15 hectares, subject to an overall maximum of £125,000.
12(b). The use of land for the storage of minerals in the open. | Applications for planning permission. | £202 for each 0.1 hectare, subject to a maximum of £30,240. | Where the site area does not exceed 15 hectares, £202 for each 0.1 hectare.
Where the site area exceeds 15 hectares, £30,240 plus £100 for each 0.1 hectare in excess of 15 hectares, subject to an overall maximum of £125,000.…
- 1 Apr 2022 – todayin force
- 19 Apr 2017 – 1 Apr 2022earlier wording