This Technical Specification for Interoperability (‘TSI’) covers the ‘operation and traffic management’ subsystem shown in the list contained in point 1 and defined in point 2.5 of Annex II to Directive (EU) 2016/797.
The geographical scope of this Regulation is the Union's network as specified in section 1 to Annex I of Directive (EU) 2016/797 and excludes the cases referred to in Article 1(3) and 1(4) of Directive (EU) 2016/797.
In accordance with Article 4(3) of Directive (EU) 2016/797, this TSI lays down the essential requirements for the ‘operation and traffic management’ subsystem and establishes the fundamental operating principles and common operating rules to the Union railway system. Furthermore, it establishes the interface requirements between infrastructure managers and railway undertakings.
This TSI applies to the Union rail system, which includes TSI conform and non-TSI conform vehicles and fixed installations.
This TSI relates to processes and procedures, as well as to physical elements of vehicles and fixed installations that are important for their operational function in the context of this TSI and requirements applicable to staff executing safety-critical tasks.
The railway undertaking and the infrastructure manager shall ensure that all requirements of this TSI become a relevant part of railway undertaking’s and infrastructure manager’s safety management system (‘SMS’) as required by Directive (EU) 2016/798.
In accordance with Article 3 of Directive (EU) 2016/797, the Union rail system, its subsystems and their interoperability constituents shall meet the essential requirements set out in general terms in Annex III to that Directive.
The essential requirements cover:
safety,
reliability and availability,
health,
environmental protection,
technical compatibility,
accessibility.
According to Directive (EU) 2016/797, the essential requirements may be generally applicable to the whole Union rail system or be specific to each subsystem and its constituents.
The following table summarises the correspondence between the essential requirements set out in Annex III to Directive (EU) 2016/797 and this Regulation.
Clause | Clause Title | Safety | Reliability & Availability | Health | Environmental protection | Technical compatibility | Accessibility | Essential requirements specific to operation and traffic management
1.1.1 | 1.1.2 | 1.1.3 | 1.1.4 | 1.1.5 | 1.2 | 1.3.1 | 1.3.2 | 1.4.1 | 1.4.2 | 1.4.3 | 1.4.4 | 1.4.5 | 1.5 | 1.6.1 | 1.6.2 | 2.6.1 | 2.6.2 | 2.6.3 | 2.6.4
4.2.1.2 | Documentation for staff executing safety-critical tasks | | | | | | X | | | | | | X | | | | | X | X | X |
4.2.1.2.1 | Rule book | | | | | | X | | | | | | X | | | | | X | | X |
4.2.1.2.2 | Route book | | | | | | | | | | | | | | | | | X | | X |
4.2.1.2.2.1 | Preparation of the Route book | | | | | | | | | | | | | | | | | X | | |
4.2.1.2.2.2 | Modification to Information contained within the route book | | | | | | | | | | | | | | | | | X | | X |
4.2.1.2.2.3 | Informing the driver in real time | | | | | | | | | | | | | | | | | X | X | X |
4.2.1.2.3 | Train running information for drivers | | | | | | | | | | | | | | | | | X | X | X |
4.2.1.2.4 | Informing the driver in real time during train operation | | | | | | | | | | | | | | | | | X | X | X |
4.2.1.3 | Documentation for railway undertaking staff other than drivers | | | | | | X | | | | | | | | | | | X | | X |
4.2.1.4 | Documentation for infrastructure manager's staff authorising train movements | | | | | | X | | | | | | | | | | | X | X | |
4.2.1.5 | Safety-related communications between train crew, other railway undertaking staff and staff authorising train movements | | | | | | X | | | | | | | | | | | X | X | X |
4.2.2.1 | Train visibility | X | | | | | | | | | | | | | | | | X | | X |
4.2.2.1.1 | General requirement | X | | | | | | | | | | | | | | | | X | | X |
4.2.2.1.2 | Front end | X | | | | | | | | | | | | | | | | X | | X |
4.2.2.1.3 | Rear end | X | | | | | | | | | | | | | | | | X | | X |
4.2.2.2 | Train audibility | X | | | | | | | | | | | X | | | | | X | | X |
4.2.2.2.1 | General requirement | X | | | | | | | | | | | | | | | | X | | X |
4.2.2.2.2 | Control | X | | | | | | | | | | | | | | | | | | X |
4.2.2.3 | Vehicle identification | | | | | | X | | | | | | | | | | | X | | X |
4.2.2.4 | Safety of passengers and load | | | | | | | | | | | | | | | | | X | | |
4.2.2.5 | Route Compatibility and Train composition | | | | | | | | | | | | | | | | | X | | |
4.2.2.5.1 | Route Compatibility | | | | | | | | | | | | | | | | | X | | |
4.2.2.5.2 | Train composition | | | | | | | | | | | | | | | | | X | | |
4.2.2.6 | Train braking | | X | | | | | | | | | | | | | | | X | | X |
4.2.2.6.1 | Minimum requirements of the braking system | | X | | | | | | | | | | | | | | | X | | X |
4.2.2.6.2 | Braking performance | | X | | | | | | | | | | | | | | | X | | X |
4.2.2.7 | Ensuring that the train is in running order | | X | | | | | | | | | | | | | | | X | | X |
4.2.2.7.1 | General requirement | | | | | | | | | | | | | | | | | X | | X |
4.2.2.7.2 | Pre-departure Data | | | | | | | | | | | | | | | | | X | | X |
4.2.2.8 | Requirements for Signal and lineside marker sighting | | | | | | | | | | | | | | X | | | X | | |
4.2.2.9 | Driver vigilance | | | | | | | | | | | | | | | | | X | | |
4.2.3.1 | Train planning and timetable | | X | | | | | | | | | | | | | | | | X | X |
4.2.3.2 | Identification of trains | | | | | | | | | | | | | | | | | X | X | X |
4.2.3.3 | Train departure | | | | | | | | | | | | | | | | | X | | X |
4.2.3.3.1 | Checks and tests before departure | | X | | | | X | | | | | | | | | | | X | | X |
4.2.3.3.2 | Informing the infrastructure manager of the train's operational status | | X | | | | X | | | | | | | | | | | | X | X |
4.2.3.4 | Traffic management | | | | | | | | | | | | | | | | | X | X | X |
4.2.3.4.1 | General requirements | | | | | | | | | | | | | | | | | X | X | X |
4.2.3.4.2 | Train reporting | | | | | | | | | | | | | | | | | X | X | X |
4.2.3.4.2.1 | Data required for train position reporting | | | | | | | | | | | | | | | | | X | | X |
4.2.3.4.2.2 | Predicted hand over time | | | | | | | | | | | | | | | | | X | | X |
4.2.3.4.3 | Dangerous goods | | | | | | | | | | | | | | | | | X | X | |
4.2.3.4.4 | Operational quality | | | | | | | | | | | | | | | | | | X | X |
4.2.3.5 | Data recording | | | | | | X | | | | | | | | | | | | X | |
4.2.3.5.1 | Recording of monitoring data outside the train | | | | | | X | | | | | | | | | | | | X | |
4.2.3.5.2 | Recording of monitoring data on-board the train | | | | | | X | | | | | | | | | | | | X | |
4.2.3.6 | Degraded operation | | | | | | | | | | | | | | | | | X | X | X |
4.2.3.6.1 | Advice to other users | | | | | | | | | | | | | | | | | X | | X |
4.2.3.6.2 | Advice to train drivers | | | | | | | | | | | | | | | | | X | | |
4.2.3.6.3 | Contingency arrangements | | | | | | | | | | | | | | | | | X | X | X |
4.2.3.7 | Managing an emergency situation | | | | | | | | | | | | | | | | | X | X | X |
4.2.3.8 | Aid to train crew in the event of an incident or of a major rolling stock malfunction | | | | | | | | | | | | | | | | | | | X |
4.4 | ERTMS operating rules | | | | | | | | | | | | | | | | | X | X | |
4.6 | Professional qualifications | | | | | | | | | | | | | | | | | X | X | X |
4.7 | Health and safety conditions | | | | | | | | | | | | | | | | | X | | |
4.8 | Additional information on infrastructure and vehicles | | | | | | | | | | | | | | | | | X | | |
4.8.1 | Infrastructure | | | | | | | | | | | | | | | | | X | | |
4.8.2 | vehicles | | | | | | | | | | | | | | | | | X | | |
In accordance with Directive 2012/34/EU of the European Parliament and of the Council [Directive 2012/34/EU of the European Parliament and of the Council of 21 November 2012 establishing a single European railway area (OJ L 343, 14.12.2012, p. 32).], it is the overall responsibility of the infrastructure manager to provide all the appropriate parameters and characteristics of the infrastructure which shall be used by the railway undertaking to check the compatibility of railway undertaking’s trains to run on infrastructure manager’s network, taking into account the geographic particularities of individual lines and the functional or technical specifications set out in this section.
The fundamental operational principles and common operational rules applicable to the Union rail network are defined in Appendix B.
The functional and technical specifications of the ‘operation and traffic management’ subsystem define the specifications to ensure safe operation, system reliability and availability and operating efficiency of the Union rail system, with focus in particular on specifications relating to:
staff executing safety-critical tasks,
trains,
train operations,
ERTMS based harmonised operation.
In its Safety Management Systems (SMS) established in accordance with Annexes I and II to Commission Delegated Regulation (EU) 2018/762 [Commission Delegated Regulation (EU) 2018/762 of 8 March 2018 establishing common safety methods on safety management system requirements pursuant to Directive (EU) 2016/798 of the European Parliament and of the Council and repealing Commission Regulations (EU) No 1158/2010 and (EU) No 1169/2010 (OJ L 129, 25.5.2018, p. 26).], each RU and IM shall identify its safety-critical tasks and safety-related functions, and the staff responsible for executing them. RUs and IMs shall define and describe in their SMS procedures and requirements to train, assess and monitor the competence of their staff executing safety-critical tasks, except the requirements laid down in the following provisions:
training, fitness and certification requirements for train drivers (addressed by Directive 2007/59/EC of the European Parliament and of the Council [Directive 2007/59/EC of the European Parliament and of the Council of 23 October 2007 on the certification of train drivers operating locomotives and trains on the railway system in the Community (OJ L 315, 3.12.2007, p. 51).]);
elements relevant to professional qualification applicable to staff ‘accompanying trains’ other than the train driver, to which Appendix F of this Annex shall apply;
elements relevant to professional qualification applicable to staff ‘preparing trains’ other than the train driver, to which Appendix G of this Annex shall apply.
Any qualification acquired based on the procedures and rules defined in the SMS of the RU or IM shall be recorded in the concerned SMS.
The documents providing evidence of training, experience and professional competences shall be delivered to the concerned staff executing safety-critical tasks, upon request.
Such a qualification shall allow the member of staff executing safety-critical tasks to undertake similar tasks for another RU or IM, subject to the identification of additional training needs on geographical and technical specifications and the SMS of the RU or IM in accordance with point 4.6.3.2, and to the satisfactory completion of that training.
IMs and RUs shall plan, prepare and operate trains and instruct staff in accordance with the information contained in Rule Book and Route Book.
Their staff executing safety-critical tasks shall be trained, and train drivers certified, based on the information provided in the Rule Book and the Route Book in accordance with their SMS.
IMs and RUs shall cooperate to exchange information and follow a process for establishing and regularly updating the Rule Book and Route Book as appropriate. Such information shall be applicable for normal, degraded and emergency operations.
The IM, in consultation with the RUs operating on its network, shall define the appropriate procedures for communication in real time and emergency situations in order to ensure that information relevant for operation is provided to the RU and/or the driver as soon as such information is available.
IMs and RUs shall ensure that all infrastructure information and rules relevant for planning, preparing and operating of trains are shared and communicated to staff executing safety-critical tasks in accordance with each staff member’s tasks in all the IMs and RUs respective operating language(s).
IM and RUs may group the Rule Book and Route Book information into support for individual staff and/or individual operations.
IMs and RUs shall supply to each member of their respective staff executing safety-critical tasks, including train drivers, with versions of the Rule Book and the Route Book tailored to the information necessary for their operations. This shall include the interface information where staff executes safety-critical tasks with a direct interface between IM and RU, in particular to ensure safety-related communication between staff authorising the movement of trains and staff onboard trains.
Future developments:
12 months after the Agency has delivered the updates to the RINF Application in accordance with Article 6(1) of Implementing Regulation (EU) 2019/777 as amended by Implementing Regulation (EU) 2023/1694 and the IMs have made the data available through RINF, RUs shall base their Route Books on the information contained in RINF.
12 months after point 1, IMs and RUs shall digitalise the Rule Book and the Route Book.
At the latest by 15 December 2025, the Agency shall deliver a Recommendation on how to harmonise the digitalisation of real time information exchange, based on Appendix C, between members of IMs’ and RUs’ staff.
The RU and the IM shall be responsible for the compilation of their respective Rule Book as integral part of their SMS to instruct staff executing safety-critical tasks, on operational rules applicable to their role.
The Rule Book is a description of the operational rules and procedures for a network or a part thereof and vehicles operated on that network or its part(s) in normal, degraded operation and emergency situations. It shall be consistent across all the lines over which the RU operates and it shall be consistent across all the lines managed by the IM.
The Rule Book shall cover:
for the RU:
the common EU safety and operating rules and procedures in accordance with Appendices A, B, C and D;
complemented by the national rules covering areas defined by Appendix I, including the IM’s instructions to the RUs on the operations of its infrastructure and the rules for managing interfaces between the IM and the RUs, all of which need to be communicated to the RUs in accordance with the IM’s SMS interface procedures;
RU instructions to the staff executing safety-critical tasks including train driver laid down in its SMS;
information relevant to the vehicles and trains operated by the RU; and
all the lines over which the RU operates;
for the IM:
the common EU safety and operating rules and procedures in accordance with Appendices A, B, C and D;
complemented by the national rules covering areas defined by Appendix I, including the rules for managing interfaces between the IM and the RUs;
IM instructions to the staff executing safety-critical tasks laid down in its SMS;
information relevant to the vehicles operated by the IM when applicable and when the IM is not acting as an RU; and
all the lines managed by the IM.
It shall include procedures covering, as a minimum, the following aspects:
staff safety and security,
signalling and control command (class A and class B systems),
train operation, including degraded mode and related to line characteristics and vehicle characteristics,
incidents and accidents, including the reporting scheme, incident or accident management plan and the detailed actions to be taken in the event of an accident or an incident,
degraded and emergency situations,
for the Rus, traction and rolling stock, including all information relevant to the operation of the rolling stock during normal and degraded mode (such as trains requiring assistance); such documentation shall also focus on the specific interface with the infrastructure manager’s staff in these cases.
It shall have two appendices:
Appendix 1: Manual of communication procedures in accordance with Appendix C1,
Appendix 2: Book of European and national instructions in accordance with Appendix C2.
Predefined messages and forms shall at least exist in the ‘operating’ language(s) of infrastructure manager(s).
If the language chosen by the railway undertaking for the Rule Book is not the language in which the appropriate information was originally supplied, it is the responsibility of the railway undertaking to arrange for any necessary translation and/or provide explanatory notes in another language.
The IM shall establish the infrastructure information covering its network for its own use and for the use of the RUs operating on this network. The IM shall provide each RU with the information for the RUs’ Route Book as defined in Appendix D2, including permanent or temporary restrictions and modifications.
The infrastructure manager shall ensure that the infrastructure information is complete and accurate; the information shall be managed in accordance with Annex II, point 4.4.3 of Delegated Regulation (EU) 2018/762.
The railway undertaking is responsible for the complete and correct compilation of the Route Book, using the information supplied by the infrastructure manager(s), in accordance with Annex I, point 4.4.3 of Delegated Regulation (EU) 2018/762. The railway undertaking shall ensure the Route Book duly describes operational conditions related to line characteristics and vehicle characteristics.
The infrastructure manager shall inform the railway undertaking of any changes to the infrastructure information, whenever such information becomes available and affects train operations, including permanent or temporary restrictions and modifications.
The IM, in consultation with the RUs operating on its network, shall define the appropriate procedures when modification of the Route Book is not transmitted from the IM to RU in the appropriate agreed timing, as defined in the SMS of the IM and reflected in the SMS of the RU; in that case, the IM shall also directly inform the driver.
RU Route Book:
Using the information received, the railway undertaking is responsible for the complete and correct compilation of the Route Book, covering the infrastructure on which it operates trains.
The railway undertaking shall ensure that the route information compiled in the Route Book consists in a description of the lines and the associated lineside equipment for the lines over which the driver will operate and relevant to the driving task.
The format of the Route Book shall be prepared in the same manner for all the infrastructures operated on by the trains of an individual railway undertaking.
When informed by the infrastructure manager of changes in the infrastructure information, the railway undertaking shall update the Route Book and communicate the modification in accordance with the procedures defined in their SMS, including instructing their drivers impacted by the change.
IM Route Book:
The IM shall compile in an IM Route Book the infrastructure information to be shared with their staff executing safety-critical tasks and compile it in accordance with its SMS.
The infrastructure manager shall update the IM Route Book, whenever such information becomes available and affects the tasks of its staff executing safety critical tasks, including permanent or temporary restrictions and modifications.
The format of the Route Book shall be prepared in the same manner for all the infrastructures worked over by the trains of an individual railway undertaking.
The railway undertaking is responsible for the complete and correct compilation of the Route book, using the information supplied by the infrastructure manager(s). The railway undertaking shall ensure that the content of the Route Book is complete and accurate, including when grouping the modifications to information contained within the Route book. The railway undertaking shall ensure the route book duly describes operational conditions related to line characteristics and vehicle characteristics.
The infrastructure manager shall provide the railway undertaking with at least the information for the route book as defined in Appendix D2 through RINF. This information shall include relevant information that shall be taken into account to adapt train operation to line characteristics and vehicle characteristics. Until RINF provides the relevant parameters in accordance with Article 6 of Commission Implementing Regulation (EU) 2019/777 [Commission Implementing Regulation (EU) 2019/777 of 16 May 2019 on the common specifications for the register of railway infrastructure and repealing Implementing Decision 2014/880/EU (See page 312 of this Official Journal).], the infrastructure manager shall provide this information through other means free of charge and as soon as reasonably possible and in any event within 15 days for the first submission unless the railway undertaking agrees a longer deadline.
The infrastructure manager shall inform the railway undertaking of the changes on the information of the route book through RINF whenever such information becomes available or through other means until RINF allows for such functionality.
The infrastructure manager shall ensure that the information provided to the railway undertaking(s) is complete and accurate. For emergency situations or real time information appropriate alternative means of communication of the infrastructure manager shall ensure immediate information to the railway undertaking about Appendix D2.
The infrastructure manager shall advise the railway undertaking of any permanent or temporary modifications to information supplied in accordance with point 4.2.1.2.2.1.
These changes shall be grouped by the railway undertaking into a dedicated document or computer medium whose format shall be the same for all the infrastructures worked over by the trains of an individual railway undertaking.
The infrastructure manager shall inform drivers of any changes to the line or relevant lineside equipment that have not been advised as modifications to information for the Route Book as set out in point 4.2.1.2.2.2.
When the railway undertaking provides the drivers with their working plan, it shall provide information necessary for the normal running of the train and as a minimum include:
the train identification,
the train running days (if necessary),
the stopping points and the activities associated with them,
other timing points,
the arrival/departure/passing times at each of those points.