The Corrective Action Plan submitted by INAC is currently being implemented. The summary of its execution in mid-April 2014 shows that 20 % of the activities planned for implementation before the end of November 2014 have been carried out as planned, while 25 % of those activities are still ongoing and the remaining 55 % have not yet started and have seen their target date significantly delayed.
114 Air carriers from São Tomé and Príncipe, Commission Implementing Regulation (EU) No 1318/2014 of 11 December 2014 amending Regula…