Directive 89/665/EEC provides for certain review procedures to be available at least to any person having or having had an interest in obtaining a particular contract and who has been or risks being harmed by an alleged infringement of Union law in the field of public procurement or national rules transposing that law. Those review procedures should not be affected by this Directive. However, citizens, concerned stakeholders, organised or not, and other persons or bodies which do not have access to review procedures pursuant to Directive 89/665/EEC do nevertheless have a legitimate interest, as taxpayers, in sound procurement procedures. They should therefore be given a possibility, otherwise than through the review system pursuant to Directive 89/665/EEC and without it necessarily involving them being given standing before courts and tribunals, to indicate possible violations of this Directive to a competent authority or structure. So as not to duplicate existing authorities or structures, Member States should be able to provide for recourse to general monitoring authorities or structures, sectoral oversight bodies, municipal oversight authorities, competition authorities, the ombudsman or national auditing authorities.
Recital 122, Directive (EU) 2014/24
Judgment of the Court (Fourth Chamber) of 26 March 2020. HUNGEOD Közlekedésfejlesztési, Földmérési, Út- és Vasúttervezési Kft. and Others v Decision
Recitals 127 and 128 of Directive 2014/25 are, in essence, identical to recitals 121 and 122 of Directive 2014/24.
26 Mar 2020 · 62018CJ0496
Opinion of Advocate General Campos Sánchez-Bordona delivered on 17 October 2024. Fastned Deutschland GmbH & Co. KG v Die Autobahn GmbH des BDecision
In the Remedies Directives, the procedural guarantee of the correct application of the provisions on public procurement is based on the reactions of economic operators who are directly affected by the breach of those provisions. [Or on the …
17 Oct 2024 · 62023CC0452
Opinion of Advocate General Bobek delivered on 21 November 2019. HUNGEOD Közlekedésfejlesztési, Földmérési, Út- és Vasúttervezési Kft. and ODecision
Recital 122 of Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing Directive 2004/18/EC [OJ 2014 L 94, p. 65.] and recital 128 of Directive 2014/25/EU of the European …
21 Nov 2019 · 62018CC0496
Judgment of the Court (Grand Chamber) of 29 April 2025. Fastned Deutschland GmbH & Co. KG v Die Autobahn GmbH des Bundes.Decision
Recital 122 of Directive 2014/24 states: ‘Directive [89/665] provides for certain review procedures to be available at least to any person having or having had an interest in obtaining a particular contract and who has been or risks …
29 Apr 2025 · 62023CJ0452
Ordonnance de la Cour (neuvième chambre) du 22 décembre 2022. Procédure engagée contre Úrad pre dohľad nad zdravotnou starostlivosťou e.a.Decision
Le considérant 122 de la directive 2014/24 est libellé ainsi : « La directive [89/665] prévoit que certaines procédures de recours sont accessibles au moins à toute personne ayant ou ayant eu intérêt à obtenir un marché …
22 Dec 2022 · 62022CO0204
- celex=31989L0655