Art. 5 Decision_act (EU) 2002/827

No longer in forcecited 2×

In accordance with Article 9(5) of Decision No 3632/93/ECSC, any payment made by Spain to González y Díez SA in anticipation of authorisation by the Commission in excess of the aid authorised for this undertaking in 2001 shall be repaid in full, by the undertaking which received it, within one month of notification of this Decision to Spain. González y Díez SA shall pay interest charges at the market rate on this amount.

  • Decision_act (EU) 2004/3406Lawamends

    Die Artikel 1, 2 und 5 der Entscheidung 2002/827/EGKS werden außer Kraft gesetzt.

  • Judgment of the Court of First Instance (Second Chamber, extended composition) of 12 September 2007. González y Díez, SA v Commission of theDecision

    The applicant adds that, given that it found it necessary to revoke Articles 1, 2 and 5 of Decision 2002/827, the Commission cannot dispute the unlawfulness of that decision.

    12 Sep 2007 · 62004TJ0025