, 1999/829/Euratom: Commission Recommendation of 6 December 1999 on the application of Art…

In forcesince 7 Dec 1999

With reference to 3.1 and 4.1 monitoring programmes as approved by the competent national authorities, organisation, sample forms and frequency, type of monitoring instruments used in normal and accident circumstances; where appropriate, any collaboration arrangements in this respect with neighbouring Member States.

9.

Radiological impact during post-closure phase

9.1. Philosophy for assuring long term safety

–

dependence placed on respective barriers, redundancy of barriers, in respect of containment of part/all of the radionuclide inventory.

9.2. Acceptance criteria applied to repository

–

use of quantitative and qualitative indicators of safety

–

use of reference groups

–

time periods considered for application of indicators.

9.3. Techniques used to evaluate long term impact of repository

–

approach to survey scenarios

–

description of scenario(s) assumed; features, events and processes taken into account, and features, events and processes deliberately omitted

–

methods used for assessment of impact

–

sources of uncertainties and approaches to managing them

–

plans for review of impact or update of safety case during the operational period up to closure.

9.4. Results of assessment of long term impact of repository

–

main exposure pathways in vicinity of repository and other Member States resulting from normal evolution (see 1.7)

–

estimated amounts, of forms of those nuclides released, estimated rate and timing of release, gas and ground water return times after closure

–

corresponding maximum exposure levels: effective doses and/or estimated risks to adults, children and infants living in relevant areas of other Member States taking account of all significant exposure pathways

–

evaluation of the uncertainties in assessments.

9.5. Authorisation procedure

–

outline of procedure to be put into place

–

limitations to be incorporated into authorisation.

9.6. Proposals for management of site post-closure

–

monitoring proposals for site post-closure

–

form and management of records.

ANNEX 4

( 1 ) OJ 81, 21.12.1960, p. 1893/60.

( 2 ) OJ L 83, 29.3.1982, p. 15.

( 3 ) OJ L 6, 9.1.1991, p. 16.

( 4 ) [1988] ECR, p. 5013.

( 5 ) OJ L 159, 29.6.1996, p. 1, to be implemented by May 2000.

( 6 ) Provided that the operation is not incorporated in a plan submitted under another heading.