, Association Agreement between the European Union and its Member States, of the one part,…

In forcesince 13 Mar 2025

Directive 2008/98/EC on waste

adoption of national legislation and designation of competent authority/ies

Timetable: these provisions of the Directive shall be implemented within 3 years of the entry into force of this Agreement.

preparation of waste management plans in line with the five-step waste hierarchy and of waste prevention programmes (Chapter V of Directive 2008/98/EC)

Timetable: these provisions of the Directive shall be implemented within 3 years of the entry into force of this Agreement.

establishment of full cost recovery mechanism in accordance with the polluter pays principle and extended producer responsibility principle (art. 14)

Timetable: these provisions of the Directive shall be implemented within 5 years of the entry into force of this Agreement.

establishment of a permitting system for establishments/undertakings carrying out disposal or recovery operations, with specific obligations for the management of hazardous wastes (Chapter IV of Directive 2008/98/EC)

Timetable: these provisions of the Directive shall be implemented within 5 years of the entry into force of this Agreement.

establishment of a register of waste collection and transport establishments and undertakings (Chapter IV of Directive 2008/98/EC)

Timetable: these provisions of the Directive shall be implemented within 5 years of the entry into force of this Agreement.

Directive 1999/31/EC on the landfill of waste as amended by Regulation (EC) 1882/2003

adoption of national legislation and designation of competent authority/ies

classification of landfill sites (art. 4)

preparation of a national strategy reducing the amount of biodegradable municipal waste going to landfill (art. 5)

establishment of an application and permit system and of waste acceptance procedures (art. 5-7, 11, 12 and 14)

establishment of control and monitoring procedures in the operation phase of landfills and of closure and after-care procedures for landfills to be disaffected (art. 12 and 13)

establishment of conditioning plans for existing landfill sites (art. 14)

establishment of a costing mechanism (art. 10)

ensuring the relevant waste is subject to treatment before landfilling (art. 6)

Timetable: these provisions of the Directive shall be implemented for existing installations within 6 years of the entry into force of this Agreement. For any installations put into operation after the signature of this agreement, the Directive's provisions shall be implemented as of the date of the agreement's entry into force.

Directive 2006/21/EC on the management of waste from extractive industries and amending Directive 2004/35/EC

adoption of national legislation and designation of competent authority/ies

establishment of a system to ensure that operators draw up waste management plans (identification and classification of waste facilities; characterisation of the waste) (art. 4 and 9)

establishment of a permit system, of financial guarantees and of an inspection system (art. 7, 14 and 17)

establishment of procedures for the management and monitoring of excavation voids (art. 10)

establishment of closure and after-closure procedures for mining waste facilities (art. 12)

drawing up an inventory of closed mining waste facilities (art. 20)

Timetable: these provisions of the Directive shall be implemented within 5 years of the entry into force of this Agreement.